RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
RegisteredMahaRERA status: Active
P51500078512
P-9 Villas · Satara (Ct), Aurangabad · Prem Infrastructures
Promised for 21 Mar 2028 and not extended so far.
1 year and 5 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
Documents 29
Show all 29 documents
OtherView
Orders 0
No MahaRERA order or list names this number.
Questions about P51500078512
Is P-9 Villas delayed?
Not so far. MahaRERA records a promised completion of 21 Mar 2028, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P51500078512.
Who is the promoter?
MahaRERA records Prem Infrastructures as the promoter of P51500078512.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P51500078512.
Answers are generated from the record.
Data through22 Oct 2026, 02:02SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology