Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Lapsed

P51500025350

Venkatesh Pride · Aurangabad (M Corp.), Aurangabad · New Arunoday Builders

Promised for 30 Jun 2024 — that date has passed and MahaRERA does not mark the project complete.

2 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Jun 2024, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Title report24 Feb 2020View
Encumbrance details24 Feb 2020View
Commencement certificate24 Feb 2020View
Form B19 Mar 2020View
Title report23 Apr 2020View
Registration certificate30 Apr 2020View
Commencement certificate9 Jun 2023View
Form 17 Mar 2026View
Show all 16 documents
Form 27 Mar 2026View
Other7 Mar 2026View
Form 2A7 Mar 2026View
Form 57 Mar 2026View
OtherView
OtherView
Layout planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500025350

Is Venkatesh Pride delayed?

Yes. MahaRERA records a promised completion of 30 Jun 2024, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500025350.

Who is the promoter?

MahaRERA records New Arunoday Builders as the promoter of P51500025350.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500025350.

Answers are generated from the record.

Data through28 Oct 2026, 02:03SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology