RegisteredCompletion date passedMahaRERA status: Lapsed

P51500022605

Yogeshwar Nagari · Soygaon, Aurangabad · Yogeswhar Builders And Developers

Promised for 30 Mar 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Mar 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 13

Title report25 Sep 2019View
Encumbrance details25 Sep 2019View
Commencement certificate25 Sep 2019View
Commencement certificate25 Sep 2019View
Commencement certificate25 Sep 2019View
Form B25 Sep 2019View
Registration certificate8 Sep 2021View
OtherView
Show all 13 documents
Layout planView
Building planView
Building planView
Building planView
Allotment letterView

Orders 0

No MahaRERA order or list names this number.

Questions about P51500022605

Is Yogeshwar Nagari delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P51500022605.

Who is the promoter?

MahaRERA records Yogeswhar Builders And Developers as the promoter of P51500022605.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P51500022605.