Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredExtendedMahaRERA status: Certificate Signed

P50500080559

Radha Krishna Nagar · Nagpur (Rural), Nagpur · R K Developers

Promised for 31 Dec 2027, extended to 30 Apr 2028, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2027 to 30 Apr 2028.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 24

Registration certificate16 Jun 2025View
Commencement certificateView
Encumbrance detailsView
Encumbrance detailsView
OtherView
OtherView
OtherView
OtherView
Show all 24 documents
OtherView
Form 1View
OtherView
OtherView
Form BView
OtherView
Layout planView
Form 1View
Form 2View
OtherView
OtherView
OtherView
OtherView
OtherView
Title reportView
Form BView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500080559

Is Radha Krishna Nagar delayed?

Its completion moved from 31 Dec 2027 to 30 Apr 2028; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500080559. The completion date moved from 31 Dec 2027 to 30 Apr 2028.

Who is the promoter?

MahaRERA records R K Developers as the promoter of P50500080559.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500080559.

Answers are generated from the record.

Data through29 Oct 2026, 02:50SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology