RegisteredMahaRERA status: Active
P50500051094
New Town · Katol (M Cl), Nagpur · Sri Balaji Developers
Promised for 31 Dec 2026 and not extended so far.
2 months to go until the promised date.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: Completion date never extended.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 45
Orders 0
No MahaRERA order or list names this number.
Questions about P50500051094
Is New Town delayed?
Not so far. MahaRERA records a promised completion of 31 Dec 2026, which has not passed yet.
How many extensions has it had?
Deedo holds 0 extension certificates for P50500051094.
Who is the promoter?
MahaRERA records Sri Balaji Developers as the promoter of P50500051094.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500051094.