Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredMahaRERA status: Certificate Signed

P50500047960

Aarambh City 2 · Nagpur (M Corp.), Nagpur · Aarambh Builders And Developers

Promised for 13 Oct 2027 and not extended so far.

1 year to go until the promised date.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 24

Registration certificate2 Dec 2022View
OtherView
OtherView
Commencement certificateView
OtherView
OtherView
Form 1View
Allotment letterView
Show all 24 documents
OtherView
OtherView
Title reportView
Title reportView
Encumbrance detailsView
Layout planView
Commencement certificateView
Form BView
Layout planView
Form 1View
OtherView
OtherView
Form 1View
Encumbrance detailsView
OtherView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500047960

Is Aarambh City 2 delayed?

Not so far. MahaRERA records a promised completion of 13 Oct 2027, which has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500047960.

Who is the promoter?

MahaRERA records Aarambh Builders And Developers as the promoter of P50500047960.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500047960.

Answers are generated from the record.

Data through28 Oct 2026, 02:33SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology