RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
P50500024514
Md Town · Besa, Nagpur · Shailendra Manohar Pulliwar
Promised for 28 Aug 2022, extended once to 31 Aug 2023 — and that date has passed without the project marked complete on MahaRERA.
4 years and 2 months past the original promise today.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- !Caution: Completion date extended from 28 Aug 2022 to 31 Aug 2023 (1 extension certificate on record).
- !Risk: The latest completion date on record, 31 Aug 2023, has passed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 22
Orders 0
No MahaRERA order or list names this number.
Questions about P50500024514
Is Md Town delayed?
Yes. MahaRERA records a promised completion of 28 Aug 2022, revised to 31 Aug 2023, which has passed, and the project is not marked complete.
How many extensions has it had?
Deedo holds 1 extension certificate for P50500024514. The completion date moved from 28 Aug 2022 to 31 Aug 2023.
Who is the promoter?
MahaRERA records Shailendra Manohar Pulliwar as the promoter of P50500024514.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50500024514.
Answers are generated from the record.