RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500016325

Rai Galaxy · Nagpur (M Corp.), Nagpur · Rai Udyog Limited

Promised for 1 Oct 2020 — that date has passed and MahaRERA does not mark the project complete.

6 years past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 1 Oct 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 15

Registration certificate18 May 2020View
OtherView
OtherView
OtherView
OtherView
Commencement certificateView
Form 1View
Building planView
Show all 15 documents
Building planView
Building planView
Building planView
Form BView
Form 1View
Layout planView
Layout planView

Orders 0

No MahaRERA order or list names this number.

Questions about P50500016325

Is Rai Galaxy delayed?

Yes. MahaRERA records a promised completion of 1 Oct 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500016325.

Who is the promoter?

MahaRERA records Rai Udyog Limited as the promoter of P50500016325.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500016325.