Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500012141

Vedant Emerald Phase 2 · Nagpur (M Corp.), Nagpur · Nanis Buildcon Private Limited

Promised for 31 Dec 2019 — that date has passed and MahaRERA does not mark the project complete.

6 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: The latest completion date on record, 31 Dec 2019, has passed.

Documents 25

Registration certificate1 Sep 2017View
OtherView
OtherView
Form 1View
OtherView
Commencement certificateView
Form 1View
Title reportView
Show all 25 documents
Encumbrance detailsView
Building planView
Form BView
Layout planView
Form 1View
Form 1View
Form 2View
Form 1View
Form 1View
Form 1View
Form 1View
Layout planView
Layout planView
OtherView
OtherView
Form 1View
Form 1View

Orders 0

No MahaRERA order or list names this number.

Questions about P50500012141

Is Vedant Emerald Phase 2 delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500012141.

Who is the promoter?

MahaRERA records Nanis Buildcon Private Limited as the promoter of P50500012141.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500012141.

Answers are generated from the record.

Data through25 Oct 2026, 03:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology