RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50500007301

Achraj Riviera · Nagpur (M Corp.), Nagpur · Ratan Constructions

Promised for 30 Dec 2021 — that date has passed and MahaRERA does not mark the project complete.

4 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 30 Dec 2021, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 22

Registration certificate9 Sep 2021View
OtherView
Commencement certificateView
OtherView
OtherView
Form 1View
OtherView
Title reportView
Show all 22 documents
Encumbrance detailsView
Layout planView
Building planView
Building planView
Form BView
Form 2View
Form 1View
Form 1View
Layout planView
Layout planView
Form 1View
OtherView
OtherView
Form 1View

Orders 0

No MahaRERA order or list names this number.

Questions about P50500007301

Is Achraj Riviera delayed?

Yes. MahaRERA records a promised completion of 30 Dec 2021, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500007301.

Who is the promoter?

MahaRERA records Ratan Constructions as the promoter of P50500007301.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500007301.

Answers are generated from the record.

Data through30 Oct 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology