RERA check · free, always
Is this project on time and in good standing?
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Completed
P50400025914
Balaji Nagari · Deoli (M Cl), Wardha · Anil Arunrao Karotkar
Promised for 30 Sep 2022; MahaRERA reports the project completed.
What to watch
Facts from the record. A flag is a reason to ask questions, not a verdict.
- ✓Clear: MahaRERA reports the project as completed.
- ✓Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.
Documents 8
Orders 0
No MahaRERA order or list names this number.
Questions about P50400025914
Is Balaji Nagari delayed?
MahaRERA reports it completed. Its promised completion date was 30 Sep 2022.
How many extensions has it had?
Deedo holds 0 extension certificates for P50400025914.
Who is the promoter?
MahaRERA records Anil Arunrao Karotkar as the promoter of P50400025914.
Is it on any MahaRERA regulatory list?
No MahaRERA order or list that Deedo holds names P50400025914.
Answers are generated from the record.
Data through29 Oct 2026, 02:07SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology