Deregistered: Krushnai Heights
matched by RERA number
View order →RERA check · free, always
Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.
Krushnai Heights · Amravati (M Corp.), Amravati · Urja Infrastructure
Promised for 31 Dec 2024, extended once to 15 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.
1 year and 10 months past the original promise today.
Facts from the record. A flag is a reason to ask questions, not a verdict.
Deregistered: Krushnai Heights
matched by RERA number
View order →Yes. MahaRERA records a promised completion of 31 Dec 2024, revised to 15 Dec 2025, which has passed, and the project is not marked complete.
Deedo holds 1 extension certificate for P50300046902. The completion date moved from 31 Dec 2024 to 15 Dec 2025.
MahaRERA records Urja Infrastructure as the promoter of P50300046902.
1 MahaRERA order or list names P50300046902.
Answers are generated from the record.