Skip to content

RERA check · free, always

Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50300028998

Geet Paradise · Amravati (M Corp.), Amravati · Geet Kamalkumar Malviya

Promised for 15 Mar 2023 — that date has passed and MahaRERA does not mark the project complete.

3 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 15 Mar 2023, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Registration certificate23 Apr 2021View
Layout planView
Building planView
Building planView
Building planView
Form 1View
Layout planView
Layout planView
Show all 16 documents
Building planView
Layout planView
Form 1View
Form 2View
OtherView
Title reportView
Form BView
Title reportView

Orders 0

No MahaRERA order or list names this number.

Questions about P50300028998

Is Geet Paradise delayed?

Yes. MahaRERA records a promised completion of 15 Mar 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50300028998.

Who is the promoter?

MahaRERA records Geet Kamalkumar Malviya as the promoter of P50300028998.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50300028998.

Answers are generated from the record.

Data through25 Oct 2026, 03:36SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology