RegisteredCompletion date passedMahaRERA status: Lapsed

P50300015082

Ishwary Colony · Amravati (M Corp.), Amravati · Sai Srujan Builders & Developers

Promised for 31 Dec 2018 — that date has passed and MahaRERA does not mark the project complete.

7 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2018, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 10

Title report29 Dec 2017View
Form B29 Dec 2017View
Commencement certificate29 Dec 2017View
Registration certificate23 Jan 2018View
Form 526 Jul 2019View
Occupancy / completion certificate18 Aug 2021View
OtherView
Layout planView
Show all 10 documents
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P50300015082

Is Ishwary Colony delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50300015082.

Who is the promoter?

MahaRERA records Sai Srujan Builders & Developers as the promoter of P50300015082.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50300015082.