Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredCompletion date passedMahaRERA status: Certificate Signed

P50300002028

Sai Heritage · Amravati (M Corp.), Amravati · Sai Datta Developers

Promised for 31 Dec 2020 — that date has passed and MahaRERA does not mark the project complete.

5 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Risk: The latest completion date on record, 31 Dec 2020, has passed.
  • Clear: Completion date never extended.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 41

Encumbrance details9 Apr 2018View
Registration certificate18 May 2020View
Layout planView
Building planView
Building planView
OtherView
OtherView
Commencement certificateView
Show all 41 documents
Commencement certificateView
OtherView
OtherView
Form 1View
Allotment letterView
OtherView
OtherView
Title reportView
Title reportView
Title reportView
Title reportView
Title reportView
Title reportView
Title reportView
Title reportView
Title reportView
Layout planView
Building planView
Building planView
Building planView
Form BView
Form BView
Layout planView
Layout planView
Form 1View
Form 1View
Form 2View
Form 1View
Form 1View
Layout planView
Encumbrance detailsView
Layout planView
Title reportView

Orders 0

No MahaRERA order or list names this number.

Questions about P50300002028

Is Sai Heritage delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2020, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 0 extension certificates for P50300002028.

Who is the promoter?

MahaRERA records Sai Datta Developers as the promoter of P50300002028.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50300002028.

Answers are generated from the record.

Data through25 Oct 2026, 01:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology