RegisteredRevised date passed1 extensionMahaRERA status: Lapsed

P50100009161

Shricharan Hieghts · Akola (M Corp.), Akola · Sanjay Shesharao Ingle

Promised for 31 Mar 2020, extended once to 31 Dec 2025 — and that date has passed without the project marked complete on MahaRERA.

6 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Mar 2020 to 31 Dec 2025 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2025, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 50

Encumbrance details31 Jul 2017View
Form B31 Jul 2017View
Form 131 Jul 2017View
Form 21 Aug 2017View
Registration certificate18 May 2020View
Allotment letter21 Oct 2022View
Commencement certificate19 Oct 2023View
Form 219 Oct 2023View
Show all 50 documents
Form 219 Oct 2023View
Form 219 Oct 2023View
Form 219 Oct 2023View
Other19 Oct 2023View
Form 519 Oct 2023View
Form 519 Oct 2023View
Form 519 Oct 2023View
Form 519 Oct 2023View
Form 519 Oct 2023View
Other19 Oct 2023View
Encumbrance details19 Oct 2023View
Allotment letter19 Oct 2023View
Form 120 Oct 2023View
Form 120 Oct 2023View
Form 120 Oct 2023View
Form 120 Oct 2023View
Form 120 Oct 2023View
Form 120 Oct 2023View
Form 123 Oct 2023View
Form 223 Oct 2023View
Form 223 Oct 2023View
Form 2A1 Nov 2023View
Form 2A1 Nov 2023View
Form 2A1 Nov 2023View
Form 2A1 Nov 2023View
Form 2A1 Nov 2023View
Form 2A1 Nov 2023View
Form 2A10 Nov 2023View
Form 2A10 Nov 2023View
Other10 Nov 2023View
Other10 Nov 2023View
Other10 Nov 2023View
Form B13 Nov 2023View
Extension certificate22 Nov 2023View
Other27 Nov 2023View
Form 2A10 Jan 2024View
Form 131 Jul 2024View
Form 2A31 Jul 2024View
Form 531 Jul 2024View
OtherView
Layout planView
Building planView

Orders 0

No MahaRERA order or list names this number.

Questions about P50100009161

Is Shricharan Hieghts delayed?

Yes. MahaRERA records a promised completion of 31 Mar 2020, revised to 31 Dec 2025, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P50100009161. The completion date moved from 31 Mar 2020 to 31 Dec 2025.

Who is the promoter?

MahaRERA records Sanjay Shesharao Ingle as the promoter of P50100009161.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50100009161.

Answers are generated from the record.

Data through25 Oct 2026, 01:37SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology