Completed

P49900025239

Shreeram Residency · Pimprala, Jalgaon · Narendra Atmaram Patil

Promised for 30 Mar 2021; MahaRERA reports the project completed.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Clear: MahaRERA reports the project as completed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 16

Title report19 Mar 2020View
Commencement certificate19 Mar 2020View
Form B19 Mar 2020View
Form 119 Mar 2020View
Form 219 Mar 2020View
Registration certificate18 May 2020View
Occupancy / completion certificate7 Oct 2021View
Form 47 Oct 2021View
Show all 16 documents
Form 529 Dec 2021View
Form 529 Dec 2021View
OtherView
Encumbrance detailsView
Layout planView
Building planView
Allotment letterView
OtherView

Orders 0

No MahaRERA order or list names this number.

Questions about P49900025239

Is Shreeram Residency delayed?

MahaRERA reports it completed. Its promised completion date was 30 Mar 2021.

How many extensions has it had?

Deedo holds 0 extension certificates for P49900025239.

Who is the promoter?

MahaRERA records Narendra Atmaram Patil as the promoter of P49900025239.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P49900025239.