Others · 1 building · 19 unitsRERA P52000014929

Sai Ganesh

Deedo IDDP-RAI-QM87

Completion was pushed back 1 year and 2 months to Oct 2020, and that date has passed too; no MahaRERA orders on record; 0% of its units are booked.

Uran, Maharashtra 400707 · Promoter: H.b. Construction

Delivery7 yrs 2 mo latePromised Aug 2019 · revised Oct 2020 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 19 units · as the promoter reported to MahaRERA
Sai Ganesh project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 1 year and 2 months to Oct 2020, and that date has passed too

  • This projectRegistered 15 Jan 2018, completion promised 1 Aug 2019, revised to 30 Oct 2020, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000014929
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200001492915 Jan 20181 Aug 201930 Oct 2020H.b. ConstructionProject page
Documents31

2 documents held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Legal

  • Declaration Form BDECLARATION.pdf · uploaded 22 Sep 2017Source
  • Legal Title reportTITLE CERTIFICATE.pdf · uploaded 22 Sep 2017Source

Migrated

  • 1 Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 22 Sep 2017Source
  • 1 Details of encumbrancesENCUMBRANCE CERTIFICATE.pdf · uploaded 22 Sep 2017Source
  • 1 Copy of Layout Approval (in case of layout)PLAN 1.pdf · uploaded 22 Sep 2017Source
  • 2 Copy of Layout Approval (in case of layout)PLAN 2.pdf · uploaded 22 Sep 2017Source
Show all 31 documentsShow fewer documents

Migrated

  • 3 Copy of Layout Approval (in case of layout)PLAN 3.pdf · uploaded 22 Sep 2017Source
  • 4 Copy of Layout Approval (in case of layout)PLAN 4.pdf · uploaded 22 Sep 2017Source
  • 1 Building Plan Approval (IOD)CC.pdf · uploaded 22 Sep 2017Source
  • 1 Declaration in FORM BDECLARATION.pdf · uploaded 22 Sep 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTS CERTIFICATE.pdf · uploaded 22 Sep 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)RCC CONSTULTANT CERTIFICATE.pdf · uploaded 22 Sep 2017Source
  • 1 Proforma of Allotment letterPROFORMA OF ALLOTMENT AND SALE AGREEMENT.pdf · uploaded 22 Sep 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 Jan 2018Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE176.pdf · uploaded 8 Jan 2018Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A)New Doc 2019-08-05 8.pdf · uploaded 5 Nov 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Audit Report FORM 5 2019.pdf · uploaded 5 Nov 2019Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDronagiri OC.pdf · uploaded 18 Feb 2020Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)form 2 engineer certificate.pdf · uploaded 15 Jul 2020Source
  • 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 15 Jul 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)img20201015_12440445.pdf · uploaded 15 Oct 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Form 4 Dronagiri project.pdf · uploaded 17 Jun 2021Source

Technical

  • DocumentCC.pdf · uploaded 22 Sep 2017Source
  • DocumentPLAN 1.pdf · uploaded 22 Sep 2017Source
  • DocumentPLAN 2.pdf · uploaded 22 Sep 2017Source
  • DocumentPLAN 3.pdf · uploaded 22 Sep 2017Source
  • DocumentPLAN 4.pdf · uploaded 22 Sep 2017Source

Technical (Architect)

  • DocumentARCHITECTS CERTIFICATE.pdf · uploaded 22 Sep 2017Source

Technical (Engineer)

  • Documentform 2 engineer certificate.pdf · uploaded 15 Jul 2020Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPLOT NO. 96 at Uran

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
1BHK, Shop19 units in all
Address
Plot No. 96, Street, UranPIN 400707
Designated bank account
105
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NO. 96 at Uran

Boundaries

North
Plot No 97
South
Plot No 95
East
Plot No 92 93
West
9m wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking19 units

0 of 19 units booked (0%), as the promoter reported to MahaRERA

1BHK · 16 unitsShop · 3 units
TypeCarpet areaUnitsBooked
1BHK27.4 sq m · 295 sq ft20
1BHK27.47 sq m · 296 sq ft10
1BHK27.48 sq m · 296 sq ft40
1BHK27.5 sq m · 296 sq ft20
1BHK27.56 sq m · 297 sq ft70
Shop12.28 sq m · 132 sq ft10
Shop15.47 sq m · 167 sq ft10
Shop19.26 sq m · 207 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKalpak Architects—
EngineerShravani Consultants—

Source: MahaRERA project page. Contact details are not shown.