Its promised completion date, Sep 2025, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Ulawe, Raigarh 410206 · Promoter: Shiv Shambhu Enterprises
Its promised completion date, Sep 2025, has passed and MahaRERA does not show it completed
- This projectRegistered 10 Jan 2023, completion promised 30 Sep 2025, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000048654
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000048654 | 10 Jan 2023 | 30 Sep 2025 | 30 Sep 2025 | Shiv Shambhu Enterprises | Project page |
Documents75
1 document held by Deedo, 74 filings listed on MahaRERA's project page
Finance
- PAN Card01 PAN CARD.pdf · uploaded 1 Oct 2022Source
Legal
Show all 75 documentsShow fewer documents
Migrated
- 1 CERSAI detailsCERSAI_Asset based.pdf · uploaded 3 Oct 2022Source
- 1 a Details of encumbrances concerned to FinanceENCUMBRANCE CERTIFICATE.pdf · uploaded 8 Oct 2022Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCE CERTIFICATE.pdf · uploaded 8 Oct 2022Source
- 1 Copy of the legal title reportTitle Report .pdf · uploaded 20 Oct 2022Source
- 1 Declaration about Commencement CertificateDECLARATION OF CC.pdf · uploaded 22 Oct 2022Source
- 1 Declaration in FORM BFORM-B.pdf · uploaded 22 Oct 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentDevelopment Aggriment.pdf · uploaded 15 Nov 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 03 CA.pdf · uploaded 22 Nov 2022Source
- 1 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 8 Dec 2022Source
- 1 Deviation Report with respect to Allotment letterdeviation-allotment.pdf · uploaded 8 Dec 2022Source
- 1 Deviation Report with respect to model copy of Agreementdeviation-draft sale.pdf · uploaded 8 Dec 2022Source
- 1 Other – LegalDA 1 to 22 (1).pdf · uploaded 8 Dec 2022Source
- 1 Proforma of Agreement for saleAFS.pdf · uploaded 19 Dec 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSHIVSHAMBHU BANK AAC DEC.pdf · uploaded 19 Dec 2022Source
- 2 Commencement Certificates / NA Order for plotted developmentshiv new cc.pdf · uploaded 31 Dec 2022Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclouser of Interest in other real estate organization.pdf · uploaded 31 Dec 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 18-07-2023.pdf · uploaded 21 Sep 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 31-03-2023 SHIVSHMBHU.pdf · uploaded 8 Nov 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 30-06-2023 shiv shmabhu.pdf · uploaded 8 Nov 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 3 30-09-2023.pdf · uploaded 8 Nov 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 31-03-2023.pdf · uploaded 8 Nov 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 30-06-2023.pdf · uploaded 8 Nov 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 30-09-2023.pdf · uploaded 8 Nov 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 9 Nov 2023Source
- 1 Disclosure of sold/ booked inventorysold unsod.pdf · uploaded 9 Nov 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31-03-2023.pdf · uploaded 9 Nov 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30-06-2023 (2).pdf · uploaded 9 Nov 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30-09-2023.pdf · uploaded 9 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5.pdf · uploaded 10 Nov 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 shiv Shambhu.pdf · uploaded 20 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Shiv Shambhu.pdf · uploaded 20 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate_Shiv shambhu Enterprises.pdf · uploaded 20 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Apr 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Orchide.pdf · uploaded 26 Apr 2024Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A.pdf · uploaded 26 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 26 Apr 2024Source
- 2 Disclosure of sold/ booked inventoryDisclosure of Sold and Unsold Inventory.pdf · uploaded 17 Jun 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate_Shiv Shambhu Revised-1.pdf · uploaded 17 Jun 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_Orchide.pdf · uploaded 2 Aug 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 2 _orchide.pdf · uploaded 2 Aug 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 _orchide.pdf · uploaded 2 Aug 2024Source
- 3 Disclosure of sold/ booked inventoryShiv Shambhu Enterprises _SOLD UNSOLD.pdf · uploaded 2 Aug 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate_Shiv Shambhu Enterprises.pdf · uploaded 2 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Orchide form 1_11zon.pdf · uploaded 7 Nov 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Shiv Shambhu Enterprises.pdf · uploaded 7 Nov 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Orchide form 2.pdf · uploaded 7 Nov 2024Source
- 2 Disclosure of sold/ booked inventoryOrchide sold_unsold Inventory .pdf · uploaded 7 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Orchide Form 1.pdf · uploaded 17 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 03.pdf · uploaded 17 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Orchide Form 2.pdf · uploaded 17 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked Inventory 230 .pdf · uploaded 18 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 12 Jul 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate_Shiv Shambhu Enterprises (2).pdf · uploaded 12 Jul 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Certificate_Shiv Shambhu Enterprises (2).pdf · uploaded 12 Jul 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 12 Jul 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 12 Jul 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A.pdf · uploaded 12 Jul 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals230
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, Shop7 units in all
- Address
- 230, Sector 19, UlwePIN 410206
- Village
- Ulawe, Panvel taluka
- Location
- 21.89740, 83.39496
- Designated bank account
- 1
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 10 Wide Road
- South
- 252 229
- East
- 231
- West
- 229
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking7 units
0 of 7 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 29.09 sq m · 313 sq ft | 1 | 0 |
| 1BHK | 29.09 sq m · 313 sq ft | 1 | 0 |
| 1BHK | 29.09 sq m · 313 sq ft | 1 | 0 |
| 1RK | 24.93 sq m · 268 sq ft | 1 | 0 |
| 1RK | 24.93 sq m · 268 sq ft | 1 | 0 |
| Shop | 7.49 sq m · 81 sq ft | 1 | 0 |
| Shop | 7.49 sq m · 81 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sheetal P Nemane | — |
| Chartered accountant | S T P And Associates | — |
| Engineer | Shravani Consultant | — |
Source: MahaRERA project page. Contact details are not shown.