Its promised completion date, Mar 2019, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 69% of its units are booked.
Ulawe, Raigarh 410206 · Promoter: Mohammed Yusuf Salim Chaudhary
Its promised completion date, Mar 2019, has passed and MahaRERA does not show it completed
- This projectRegistered 16 Aug 2017, completion promised 31 Mar 2019, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000006659
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000006659 | 16 Aug 2017 | 31 Mar 2019 | 31 Mar 2019 | Mohammed Yusuf Salim Chaudhary | Project page |
Documents38
1 document held by Deedo, 37 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 31 Jul 2017Source
Legal
Show all 38 documentsShow fewer documents
Migrated
- 2 Copy of the legal title reportTITLE CERTIFICATE-2.pdf · uploaded 31 Jul 2017Source
- 1 Details of encumbrancesDETAILS OF ENCUMBRANCES.pdf · uploaded 31 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN.pdf · uploaded 31 Jul 2017Source
- 1 Building Plan Approval (IOD)COMMECEMENT CERTIFICATE-1.pdf · uploaded 31 Jul 2017Source
- 2 Building Plan Approval (IOD)COMMECEMENT CERTIFICATE-2.pdf · uploaded 31 Jul 2017Source
- 3 Building Plan Approval (IOD)COMMECEMENT CERTIFICATE-3.pdf · uploaded 31 Jul 2017Source
- 1 Declaration in FORM BDECLARATION FROM B.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECHTS CERTIFICATE.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE-1.pdf · uploaded 31 Jul 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE-2.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE -1.pdf · uploaded 31 Jul 2017Source
- 2 Certificates of CA (Form 3)CA CERTIFICATE -2.pdf · uploaded 31 Jul 2017Source
- 1 Proforma of Allotment letterRERA AGREEMENT - NEXUS.pdf · uploaded 31 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCommence Certificate.pdf · uploaded 11 Oct 2018Source
- 2 Commencement Certificates / NA Order for plotted developmentCommence Certificate-2.pdf · uploaded 11 Oct 2018Source
- 3 Commencement Certificates / NA Order for plotted developmentCommence Certificate-3.pdf · uploaded 11 Oct 2018Source
- 4 Commencement Certificates / NA Order for plotted developmentCommence Certificate-ilovepdf-compressed.pdf · uploaded 11 Oct 2018Source
- 1 OtherOccupancy Certificate.pdf · uploaded 11 Oct 2018Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentNexus OC Certificate.pdf · uploaded 5 May 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY FORMATION.pdf · uploaded 5 May 2022Source
- 1 Proforma of Agreement for sale1 Proforma of Agreement of sale.pdf · uploaded 13 Apr 2023Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD INVENTORY.pdf · uploaded 14 Oct 2023Source
- 2 Disclosure of sold/ booked inventoryFLAT SALES DETAILS.pdf · uploaded 14 Oct 2023Source
- 5 Architect’s Certificate on Completion of Project (Form 4)Architect Certificate.pdf · uploaded 23 Oct 2023Source
Technical
Technical (Architect)
- DocumentARCHITECHTS CERTIFICATE.pdf · uploaded 31 Jul 2017Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE-2.pdf · uploaded 31 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals304
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- Flat16 units in all
- Address
- 304PIN 410206
- Village
- Ulawe, Panvel taluka
- Location
- 18.97509, 73.05233
- Designated bank account
- 229
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 303
- South
- Plot No 305
- East
- 9 Meter Road
- West
- 11 Meter Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
11 of 16 units booked (69%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Flat | 440.24 sq m · 4,739 sq ft | 16 | 11 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Soyuz T Talib | — |