Residential / Group Housing · 1 building · 14 unitsRERA P52000023957

Matrix Homes

Deedo IDDP-RAI-8JZC

Its promised completion date, Oct 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.

Ulawe, Raigarh 410206 · Promoter: Matrix Infra

Delivery3 yrs past duePromised Oct 2023 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 14 units · as the promoter reported to MahaRERA
Matrix Homes project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Oct 2023, has passed and MahaRERA does not show it completed

  • This projectRegistered 14 Jan 2020, completion promised 30 Oct 2023, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000023957
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002395714 Jan 202030 Oct 202330 Oct 2023Matrix InfraProject page
Documents38

1 document held by Deedo, 37 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardMATRIX INFRA PAN CARD.pdf · uploaded 4 Jan 2020Source

Legal

  • Legal Title reportTITILE CLEARANCE CERTIFICATE.pdf · uploaded 4 Jan 2020Source
  • Declaration Form BFORM B.pdf · uploaded 4 Jan 2020Source

Migrated

  • 1 PAN CardMATRIX INFRA PAN CARD.pdf · uploaded 4 Jan 2020Source
  • 1 Copy of the legal title reportTITILE CLEARANCE CERTIFICATE.pdf · uploaded 4 Jan 2020Source
  • 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 4 Jan 2020Source
  • 1 Copy of Layout Approval (in case of layout)CC DRAWING.pdf · uploaded 4 Jan 2020Source
Show all 38 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentCC DRAWING.pdf · uploaded 4 Jan 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC CERTIFICATE .pdf · uploaded 4 Jan 2020Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 4 Jan 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 4 Jan 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PAGE 1.pdf · uploaded 4 Jan 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PAGE 2.pdf · uploaded 4 Jan 2020Source
  • 1 Proforma of Allotment letterDRAFT AGREEMENT DATED.pdf · uploaded 4 Jan 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Matrix Homes.pdf · uploaded 7 Jan 2020Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 Jan 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 28 Oct 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1FORM NO-01 31-3-2020.pdf · uploaded 16 Feb 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2FORM NO-01 31-3-21.pdf · uploaded 16 Feb 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3FORM NO-01 31-12-2021.pdf · uploaded 16 Feb 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)4FORM NO-01 31-03-2022.pdf · uploaded 16 Feb 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1FORM NO-03 31-03-2020.pdf · uploaded 16 Feb 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)2FORM NO-03 31-03-2021.pdf · uploaded 16 Feb 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)3FORM NO-03 21-12-2021.pdf · uploaded 16 Feb 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)4FORM NO-03 31-12-2022_compressed.pdf · uploaded 16 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)1FORM NO-05 31-03-2020.pdf · uploaded 16 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)2FORM NO-05 31-03-2021.pdf · uploaded 16 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)3FORM NO-05 31-03-2022.pdf · uploaded 16 Feb 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM NO-04.pdf · uploaded 16 Feb 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 FORM-2 31-03-2020.pdf · uploaded 17 Feb 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 FORM -2 31-03-2021.pdf · uploaded 17 Feb 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 FORM-2 21-12-2021.pdf · uploaded 17 Feb 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 FORM-2 31-12-2022.pdf · uploaded 17 Feb 2023Source

Technical

  • DocumentCC DRAWING.pdf · uploaded 4 Jan 2020Source
  • DocumentCC DRAWING.pdf · uploaded 4 Jan 2020Source

Technical (Architect)

  • Document4FORM NO-01 31-03-2022.pdf · uploaded 16 Feb 2023Source

Technical (Engineer)

  • Document4 FORM-2 31-12-2022.pdf · uploaded 17 Feb 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPLOT NOC36, SECTOR08

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK14 units in all
Address
Plot No-C36, Sector-08, Sector 8, Navi MumbaiPIN 410206
Village
Ulawe, Panvel taluka
Designated bank account
85
Developed in phases
No

Survey, CTS, gat or plot numbers

PLOT NOC36SECTOR08

Boundaries

North
Plot No C 35
South
Plot No C 37
East
11 Sq Mtrs Wide Road
West
Plot No C 41

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking14 units

0 of 14 units booked (0%), as the promoter reported to MahaRERA

1BHK · 7 units1RK · 7 units
TypeCarpet areaUnitsBooked
1BHK24.59 sq m · 265 sq ft30
1BHK24.59 sq m · 265 sq ft40
1RK15.93 sq m · 171 sq ft10
1RK16.09 sq m · 173 sq ft30
1RK17.07 sq m · 184 sq ft10
1RK17.07 sq m · 184 sq ft10
1RK18.24 sq m · 196 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel—
Chartered accountantDnj & Associates—
EngineerB S Sukthankar—
OtherSRBS Construction Pvt Ltd—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology