Matrix Homes
Deedo IDDP-RAI-8JZCIts promised completion date, Oct 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Ulawe, Raigarh 410206 · Promoter: Matrix Infra
Its promised completion date, Oct 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 14 Jan 2020, completion promised 30 Oct 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000023957
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000023957 | 14 Jan 2020 | 30 Oct 2023 | 30 Oct 2023 | Matrix Infra | Project page |
Documents38
1 document held by Deedo, 37 filings listed on MahaRERA's project page
Finance
- PAN CardMATRIX INFRA PAN CARD.pdf · uploaded 4 Jan 2020Source
Legal
Migrated
- 1 PAN CardMATRIX INFRA PAN CARD.pdf · uploaded 4 Jan 2020Source
- 1 Copy of the legal title reportTITILE CLEARANCE CERTIFICATE.pdf · uploaded 4 Jan 2020Source
- 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 4 Jan 2020Source
- 1 Copy of Layout Approval (in case of layout)CC DRAWING.pdf · uploaded 4 Jan 2020Source
Show all 38 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentCC DRAWING.pdf · uploaded 4 Jan 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCC CERTIFICATE .pdf · uploaded 4 Jan 2020Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 4 Jan 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 4 Jan 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PAGE 1.pdf · uploaded 4 Jan 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PAGE 2.pdf · uploaded 4 Jan 2020Source
- 1 Proforma of Allotment letterDRAFT AGREEMENT DATED.pdf · uploaded 4 Jan 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Matrix Homes.pdf · uploaded 7 Jan 2020Source
- 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 Jan 2020Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 28 Oct 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1FORM NO-01 31-3-2020.pdf · uploaded 16 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2FORM NO-01 31-3-21.pdf · uploaded 16 Feb 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3FORM NO-01 31-12-2021.pdf · uploaded 16 Feb 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)4FORM NO-01 31-03-2022.pdf · uploaded 16 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)1FORM NO-03 31-03-2020.pdf · uploaded 16 Feb 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)2FORM NO-03 31-03-2021.pdf · uploaded 16 Feb 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)3FORM NO-03 21-12-2021.pdf · uploaded 16 Feb 2023Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)4FORM NO-03 31-12-2022_compressed.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)1FORM NO-05 31-03-2020.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)2FORM NO-05 31-03-2021.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)3FORM NO-05 31-03-2022.pdf · uploaded 16 Feb 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM NO-04.pdf · uploaded 16 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 FORM-2 31-03-2020.pdf · uploaded 17 Feb 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 FORM -2 31-03-2021.pdf · uploaded 17 Feb 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 FORM-2 21-12-2021.pdf · uploaded 17 Feb 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 FORM-2 31-12-2022.pdf · uploaded 17 Feb 2023Source
Technical
Technical (Architect)
- Document4FORM NO-01 31-03-2022.pdf · uploaded 16 Feb 2023Source
Technical (Engineer)
- Document4 FORM-2 31-12-2022.pdf · uploaded 17 Feb 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPLOT NOC36, SECTOR08
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK14 units in all
- Address
- Plot No-C36, Sector-08, Sector 8, Navi MumbaiPIN 410206
- Village
- Ulawe, Panvel taluka
- Designated bank account
- 85
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No C 35
- South
- Plot No C 37
- East
- 11 Sq Mtrs Wide Road
- West
- Plot No C 41
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking14 units
0 of 14 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 24.59 sq m · 265 sq ft | 3 | 0 |
| 1BHK | 24.59 sq m · 265 sq ft | 4 | 0 |
| 1RK | 15.93 sq m · 171 sq ft | 1 | 0 |
| 1RK | 16.09 sq m · 173 sq ft | 3 | 0 |
| 1RK | 17.07 sq m · 184 sq ft | 1 | 0 |
| 1RK | 17.07 sq m · 184 sq ft | 1 | 0 |
| 1RK | 18.24 sq m · 196 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel | — |
| Chartered accountant | Dnj & Associates | — |
| Engineer | B S Sukthankar | — |
| Other | SRBS Construction Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.