Deedo IDDP-RAI-X9FMIts promised completion date, Dec 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 50% of its units are booked.
Ulawe, Raigarh 410206 · Promoter: Jay Ambe Developers
Its promised completion date, Dec 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 14 Nov 2022, completion promised 31 Dec 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000047632
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000047632 | 14 Nov 2022 | 31 Dec 2023 | 31 Dec 2023 | Jay Ambe Developers | Project page |
Documents35
1 document held by Deedo, 34 filings listed on MahaRERA's project page
Finance
- PAN CardPAN of Firm.pdf · uploaded 28 Sep 2022Source
Legal
Migrated
- 1 PAN CardPAN of Firm.pdf · uploaded 28 Sep 2022Source
- 1 Copy of the legal title reportTitle Report Jay Ambe.pdf · uploaded 28 Sep 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 28 Sep 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout Plan.pdf · uploaded 28 Sep 2022Source
Show all 35 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 28 Sep 2022Source
- 1 Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 28 Sep 2022Source
- 1 Declaration in FORM BForm B Promoter.pdf · uploaded 28 Sep 2022Source
- 1 CERSAI detailsCERSAI Report.pdf · uploaded 28 Sep 2022Source
- 1 a Details of encumbrances concerned to FinanceEncumbrance Letter Final.pdf · uploaded 29 Sep 2022Source
- 1 b Details of encumbrances concerned to LegalEncumbrance Letter Final.pdf · uploaded 29 Sep 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Details Final.pdf · uploaded 29 Sep 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate - Dated.pdf · uploaded 6 Oct 2022Source
- 1 Proforma of Allotment letterDraft Allotment Letter with Annexue A.pdf · uploaded 1 Nov 2022Source
- 1 Deviation Report with respect to Allotment letterNo Deviation Allotment Letter.pdf · uploaded 1 Nov 2022Source
- 1 Deviation Report with respect to model copy of AgreementNo Deviation AFS.pdf · uploaded 1 Nov 2022Source
- 1 Proforma of Agreement for saleDraft Agreement For Sale.pdf · uploaded 10 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 4 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form-2.pdf · uploaded 4 Feb 2023Source
- 1 Disclosure of sold/ booked inventoryInventory sold letter.pdf · uploaded 17 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5-with sign.pdf · uploaded 29 Sep 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 24 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -1.pdf · uploaded 10 Apr 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentoc.pdf · uploaded 10 Apr 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 13 Apr 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)248-24-PUSHPAK FORM 4.pdf · uploaded 20 Apr 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 30 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Final form 5.pdf · uploaded 30 Nov 2024Source
Technical
Technical (Architect)
- DocumentFORM -1.pdf · uploaded 10 Apr 2024Source
Technical (Engineer)
- Documentform 2.pdf · uploaded 13 Apr 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPLOT NO 248
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, Shop20 units in all
- Address
- Plot No 248, Plot No-248, Sector-24, Pushpak-Vahal, UlwePIN 410206
- Village
- Ulawe, Panvel taluka
- Location
- 18.96898, 73.03850
- Designated bank account
- 148
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 247
- South
- Plot No 249
- East
- Plot No 261
- West
- 9 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking20 units
10 of 20 units booked (50%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 24.15 sq m · 260 sq ft | 12 | 6 |
| 1RK | 15.91 sq m · 171 sq ft | 2 | 2 |
| 1RK | 18.29 sq m · 197 sq ft | 2 | 0 |
| Shop | 9.35 sq m · 101 sq ft | 4 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel Architects | — |
| Chartered accountant | V M Patel & Associates | — |
| Engineer | B S Sukthankar & Associates | — |
Source: MahaRERA project page. Contact details are not shown.