Skip to content

RERA projects in Sanaswadi

1 project under 1 MahaRERA registration, registered 2017–2017. None has an extended completion date on record.

Locality
1RERA projects
1Registrations
0Completion still due1 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20171

Projects in Sanaswadi

1 project registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Gold Valley KonkanGoka Engineering Co Pvt LtdP5200000533113 Nov 201731 Dec 201731 Dec 2017Promised date passed0

Other localities in Mangaon

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Goka Engineering Co Pvt Ltd1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology