RERA projects in Roha
125 projects under 127 MahaRERA registrations, registered 2017–2026. 11% have a completion date extended beyond the one promised.
125RERA projects
127Registrationssome projects hold several
51Completion still due61 past their completion date
36 monthsMedian extension beyond promised date11% of registrations extended
2Regulatory caseson 2 projects
12Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 31 |
| 2018 | 7 |
| 2019 | 5 |
| 2020 | 7 |
| 2021 | 7 |
| 2022 | 15 |
| 2023 | 11 |
| 2024 | 13 |
| 2025 | 10 |
| 2026 | 6 |
Projects in Roha
125 projects registered with MahaRERA in this taluka and the places within it.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Shree Balaji HieghtsRajendra Sitaram Sawant | P52000005765 | 11 Aug 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Garva Residency-B2Garva Developers Pvt Ltd | P52000004481 | 9 Aug 2017 | 31 Jan 2018 | — | Promised date passed | 0 |
| Platinum GharondaJay Gurudev Constructions | P52000004277 | 9 Aug 2017 | 30 Sep 2020 | — | Promised date passed | 0 |
| Ekdanta PlazaEkdanta Realtors | P52000003500 | 5 Aug 2017 | 30 Dec 2020 | 31 Dec 2026 | Extended 72 mo | 0 |
| Nirman Vimla KantiNirman Construction | P52000003155 | 4 Aug 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| The Pearl ParkLiyakat Anwar Hafiz | P52000002484 | 1 Aug 2017 | 30 Dec 2020 | — | Promised date passed | 0 |
| Roha GreenAbs Group | P52000002271 | 31 Jul 2017 | 30 Sep 2020 | — | Promised date passed | 0 |
| Ramchandra Residency Phase 1Crk Infrastructure | P52000001918 | 29 Jul 2017 | 31 Mar 2019 | 30 Sep 2020 | Extended 18 mo | 0 |
| Nirman - DineshNirman Construction | P52000000597 | 18 Jul 2017 | 30 Dec 2021 | — | Promised date passed | 0 |
| Anand ParkAadinath Builders and Developers | P52000000187 | 10 Jul 2017 | 30 Dec 2020 | — | Promised date passed | 0 |
| Chetan Rachana | P52000019528 | — | — | — | — | 0 |
| Green Park Residency | P52000009608 | — | — | — | — | 0 |
| Krishnakant Darshan Park | P52000004318 | — | — | — | — | 0 |
| Mannat Apartments | P52000010563 | — | — | — | — | 0 |
| P52000007931 | P52000007931 | — | — | — | — | 0 |
| Parmar Sky | P52000005171 | — | — | — | — | 0 |
| Roha Mega City Phase IIA-B | P52000010651 | — | — | — | — | 0 |
| Roshni Galaxy | P52000011392 | — | — | — | — | 0 |
| Shalom Tower | P52000027676 | — | — | — | — | 0 |
| Shree Jogeshwari Residency | P52000024302 | — | — | — | — | 0 |
| Shree Ramchandra Residency Phase II | P52000029169 | — | — | — | — | 0 |
| Shree Swami Samarth Apartment | P52000017254 | — | — | — | — | 0 |
| Sunderban | P52000004675 | — | — | — | — | 0 |
| Vardhaman Heights | P52000024846 | — | — | — | — | 0 |
| Vishwamahal Residency | P52000010067 | — | — | — | — | 0 |
Other talukas in Raigarh
Most active promoters
By projects registered here, as named on MahaRERA.
- Liyakat Anwar Hafiz4 projects
- Garva Developers Pvt Ltd3 projects
- Nirman Construction3 projects
- Ekdanta Realtors2 projects
- Garva Land Deal Private Limited2 projects
- K K Constructions2 projects
- Mdsk Builders And Developers2 projects
- Sanjay Ramchandra Dalavi2 projects
- Shreekrupa Realtors Private Limited2 projects
- Shree Rajendra Developers2 projects
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology