Happy Homes
Deedo IDDP-RAI-D2V0Completion was pushed back 3 years to Mar 2026, and that date has passed too; no MahaRERA orders on record; 56% of its units are booked.
Rees, Raigarh 410222 · Promoter: Harjinder Kaur Charandeep Singh
Completion was pushed back 3 years to Mar 2026, and that date has passed too
- This projectRegistered 26 Apr 2021, completion promised 31 Mar 2023, revised to 30 Mar 2026, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000029102
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000029102 | 26 Apr 2021 | 31 Mar 2023 | 30 Mar 2026 | Harjinder Kaur Charandeep Singh | Project page |
Documents60
2 documents held by Deedo, 58 filings listed on MahaRERA's project page
Finance
- PAN CardHARJINDER PANCARD.pdf · uploaded 22 Mar 2021Source
Legal
- Declaration Form BHAPPAY HOMES PROMOTER FORM B .pdf · uploaded 24 Mar 2021Source
- Legal Title reporttitle report_compressed.pdf · uploaded 16 Apr 2021Source
- Declaration Form BScan 15 May 24 16·48·18.pdf · uploaded 15 May 2024Source
- Declaration Form BForm B Happy Homes_11zon.pdf · uploaded 2 Jul 2024Source
Migrated
- 1 PAN CardHARJINDER PANCARD.pdf · uploaded 22 Mar 2021Source
Show all 60 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)PG 1 (2).pdf · uploaded 22 Mar 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPLAN MERGED.pdf · uploaded 22 Mar 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCC HAPPY HOMES_compressed.pdf · uploaded 22 Mar 2021Source
- 1 Details of encumbrancesHAPPY HOMES ENCUMBRANCE .pdf · uploaded 24 Mar 2021Source
- 1 Declaration in FORM BHAPPAY HOMES PROMOTER FORM B .pdf · uploaded 24 Mar 2021Source
- 1 Copy of the legal title reporttitle report_compressed.pdf · uploaded 16 Apr 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 HAPPY HOMES.pdf · uploaded 19 Apr 2021Source
- 1 Proforma of Allotment letterATS_Happy Homes.pdf · uploaded 20 Apr 2021Source
- 2 Proforma of Allotment letterHappy Homes_Allotment letter.pdf · uploaded 20 Apr 2021Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 2 May 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Happy Homes as on March 2023.pdf · uploaded 2 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A 21-22.pdf · uploaded 2 May 2023Source
- 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 2 May 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Happy Homes as on 31-03-2023.pdf · uploaded 2 May 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 - Happy Homes FY 2021-22.pdf · uploaded 6 May 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Revised_New Format Form 3 - Final Happy Homes as on 31-03-2023.pdf · uploaded 8 May 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A 22-23.pdf · uploaded 14 May 2024Source
- 1 CERSAI detailsDeclaration of CERSAI .pdf · uploaded 14 May 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 14 May 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 14 May 2024Source
- 2 Declaration in FORM BScan 15 May 24 16·48·18.pdf · uploaded 15 May 2024Source
- 3 Declaration in FORM BForm B Happy Homes_11zon.pdf · uploaded 2 Jul 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Jul 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mar_11zon.pdf · uploaded 2 Jul 2024Source
- 2 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 2 Jul 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar_11zon.pdf · uploaded 2 Jul 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23_11zon.pdf · uploaded 2 Jul 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)11zon_removed-pages-PDF.pdf · uploaded 2 Jul 2024Source
- Form 1202508281252.pdf · uploaded 1 Sep 2025Source
- Form 2Form 2 - Happy Homes as on June 2025.pdf · uploaded 1 Sep 2025Source
- Form 34 CA Certificate on Project Cost & Fund withdrawal (Form 3) (5).pdf · uploaded 1 Sep 2025Source
- Disclosure of Sold and Booked Inventory2 Disclosure of sold_ booked inventory.pdf · uploaded 1 Sep 2025Source
- Self-declaration of Quarterly ProgressQPR Declaration.pdf · uploaded 1 Sep 2025Source
- Withdrawal Update Form 1Form 1 - March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 1Form 1 - March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 1Form 1 - March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 2Form 2- March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 2Form 2- March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 2Form 2- March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 3Form 3- March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 3Form 3- March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 3Form 3- March Quarter 2026.pdf · uploaded 29 Sep 2026Source
- Withdrawal Update Form 1Form 1 June quarter 2026.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 1form 1.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2Form 2 June quarter 2026.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 2form 2.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3Form 3 June quarter 2026.pdf · uploaded 6 Oct 2026Source
- Withdrawal Update Form 3form 3.pdf · uploaded 6 Oct 2026Source
Technical
Technical (Architect)
- Documentform 1.pdf · uploaded 6 Oct 2026Source
Technical (Engineer)
- Documentform 2.pdf · uploaded 6 Oct 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPlot No 126/5
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK25 units in all
- Address
- Plot No - 126/5, Plot No -126/5, KhalapurPIN 410222
- Village
- Rees, Khalapur taluka
- Location
- 18.90456, 73.20854
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Survey No - 125 Part
- South
- Survey No - 125
- East
- Survey No -127
- West
- 7 point 50 Mtr wide road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking25 units
14 of 25 units booked (56%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 25.77 sq m · 277 sq ft | 3 | 1 |
| 1BHK | 25.78 sq m · 277 sq ft | 2 | 2 |
| 1BHK | 25.85 sq m · 278 sq ft | 2 | 0 |
| 1BHK | 26.18 sq m · 282 sq ft | 3 | 1 |
| 1BHK | 26.22 sq m · 282 sq ft | 3 | 0 |
| 1BHK | 26.47 sq m · 285 sq ft | 2 | 2 |
| 1BHK | 28.42 sq m · 306 sq ft | 5 | 4 |
| 1BHK | 34.7 sq m · 374 sq ft | 5 | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Mandar V Bodhankar | — |
| Chartered accountant | Rutuja Narsingh & Associates | — |
| Engineer | Shridhar Murthy | — |
Source: MahaRERA project page. Contact details are not shown.