Its promised completion date, Dec 2018, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 33% of its units are booked.

Patnoli, Raigarh 410206 · by Dg Enterprises

Delivery7 yrs 10 mo past duePromised Dec 2018 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales33% booked5 of 15 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Its promised completion date, Dec 2018, has passed and MahaRERA does not show it completed

  • This projectRegistered 18 Aug 2017, completion promised 31 Dec 2018, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000007969
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000796918 Aug 201731 Dec 201831 Dec 2018DG EnterprisesProject page
Documents27

1 document held by Deedo, 26 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardCOMPANY PANCARD.pdf · uploaded 21 Jul 2017Source

Legal

  • Legal Title reportSearch Report.pdf · uploaded 22 Jul 2017Source
  • Declaration Form BForm B.pdf · uploaded 29 Jul 2017Source

Migrated

  • 1 PAN CardCOMPANY PANCARD.pdf · uploaded 21 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Certificates of Architect (Form 1).pdf · uploaded 21 Jul 2017Source
  • 1 Copy of the legal title reportSearch Report.pdf · uploaded 22 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)PLOT NO 295 RERA DRAWING 1.pdf · uploaded 22 Jul 2017Source
Show all 27 documentsShow fewer documents

Migrated

  • 2 Copy of Layout Approval (in case of layout)PLOT NO 295 RERA DRAWING 2.pdf · uploaded 22 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)PLOT NO 295 RERA DRAWING 3.pdf · uploaded 22 Jul 2017Source
  • 1 Building Plan Approval (IOD)BPL2.pdf · uploaded 22 Jul 2017Source
  • 2 Building Plan Approval (IOD)BAP1.pdf · uploaded 22 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 22 Jul 2017Source
  • 1 Details of encumbrancesEncumbrances Certificate.pdf · uploaded 27 Jul 2017Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer's Certificate.pdf · uploaded 29 Jul 2017Source
  • 1 Proforma of Allotment letterSAI SPARSH NEW DRAFT RERA.pdf · uploaded 29 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 30 Jul 2017Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)form 4 (2).pdf · uploaded 7 Feb 2020Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentDG OC.pdf · uploaded 10 Feb 2020Source

Technical

  • DocumentBPL2.pdf · uploaded 22 Jul 2017Source
  • DocumentBAP1.pdf · uploaded 22 Jul 2017Source
  • DocumentPLOT NO 295 RERA DRAWING 1.pdf · uploaded 22 Jul 2017Source
  • DocumentPLOT NO 295 RERA DRAWING 2.pdf · uploaded 22 Jul 2017Source
  • DocumentPLOT NO 295 RERA DRAWING 3.pdf · uploaded 22 Jul 2017Source

Technical (Architect)

  • DocumentCertificates of Architect (Form 1).pdf · uploaded 21 Jul 2017Source

Technical (Engineer)

  • DocumentEngineer's Certificate.pdf · uploaded 29 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 295

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Residential15 units in all
Address
295PIN 410206
Village
Ulawe, Panvel taluka
Designated bank account
1
Developed in phases
No

Survey, CTS, gat or plot numbers

295

Boundaries

North
296
South
294
East
278
West
11 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking15 units

5 of 15 units booked (33%), as the promoter reported to MahaRERA

Residential · 15 units
TypeCarpet areaUnitsBooked
Residential343.42 sq m · 3,697 sq ft155

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDeepali Chawak—
EngineerB S Sukthankar—
OtherNagraj Bhagat—

Source: MahaRERA project page. Contact details are not shown.