Deedo IDDP-RAI-AFXZIts promised completion date, Jun 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 38% of its units are booked.
Panvel, Maharashtra 410206 · Promoter: K And S Infra
Its promised completion date, Jun 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 14 Jun 2019, completion promised 30 Jun 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000021220
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000021220 | 14 Jun 2019 | 30 Jun 2023 | 30 Jun 2023 | K And S Infra | Project page |
Documents47
1 document held by Deedo, 46 filings listed on MahaRERA's project page
Finance
- PAN CardKNS Pan Card.pdf · uploaded 31 May 2019Source
Legal
Migrated
- 1 PAN CardKNS Pan Card.pdf · uploaded 31 May 2019Source
- 1 Copy of the legal title reportTitle Search Report.pdf · uploaded 31 May 2019Source
- 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 31 May 2019Source
- 1 Copy of Layout Approval (in case of layout)IOD1.pdf · uploaded 31 May 2019Source
Show all 47 documentsShow fewer documents
Migrated
- 2 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 31 May 2019Source
- 1 Building Plan Approval (IOD)IOD1.pdf · uploaded 31 May 2019Source
- 2 Building Plan Approval (IOD)IOD2.pdf · uploaded 31 May 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 May 2019Source
- 1 Declaration in FORM BForm B.pdf · uploaded 31 May 2019Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 31 May 2019Source
- 1 Proforma of Allotment letterAFS1.pdf · uploaded 31 May 2019Source
- 2 Proforma of Allotment letterAFS2.pdf · uploaded 31 May 2019Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Certificate.pdf · uploaded 19 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 032020.pdf · uploaded 16 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 032021.pdf · uploaded 16 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 122021.pdf · uploaded 16 Feb 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 032022.pdf · uploaded 16 Feb 2023Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 062022.pdf · uploaded 16 Feb 2023Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 092022.pdf · uploaded 16 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 032020.pdf · uploaded 16 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 032021.pdf · uploaded 16 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 122021.pdf · uploaded 16 Feb 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 032022.pdf · uploaded 16 Feb 2023Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 062022.pdf · uploaded 16 Feb 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 092022.pdf · uploaded 16 Feb 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 122022.pdf · uploaded 16 Feb 2023Source
- 2 Certificates of CA (Form 3)FORM 3 032020.pdf · uploaded 16 Feb 2023Source
- 3 Certificates of CA (Form 3)FORM 3 032021.pdf · uploaded 16 Feb 2023Source
- 4 Certificates of CA (Form 3)FORM 3 122021.pdf · uploaded 16 Feb 2023Source
- 5 Certificates of CA (Form 3)FORM 3 032022.pdf · uploaded 16 Feb 2023Source
- 6 Certificates of CA (Form 3)FORM 3 062022.pdf · uploaded 16 Feb 2023Source
- 7 Certificates of CA (Form 3)FORM 3 092022.pdf · uploaded 16 Feb 2023Source
- 8 Certificates of CA (Form 3)FORM 3 122022.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 032020.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 032021.pdf · uploaded 16 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 032022.pdf · uploaded 16 Feb 2023Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 12 Apr 2023Source
Technical
Technical (Architect)
- DocumentFORM 1 092022.pdf · uploaded 16 Feb 2023Source
Technical (Engineer)
- DocumentFORM 2 122022.pdf · uploaded 16 Feb 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals191 at Panvel
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1 BHK, 1 RK WITH TERRACE, Shop no 1, Shop no 2, Shop no 3, Shop no 424 units in all
- Address
- 191, Plot No 191, Sector R3, , Pushpak (New)PIN 410206
- Designated bank account
- 220
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 9 Mtr Wide Road
- South
- Plot No 195
- East
- Plot No 192
- West
- Plot No 190
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking24 units
9 of 24 units booked (38%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 24.26 sq m · 261 sq ft | 3 | 2 |
| 1 BHK | 25.25 sq m · 272 sq ft | 1 | 0 |
| 1 BHK | 25.67 sq m · 276 sq ft | 6 | 2 |
| 1 BHK | 28.06 sq m · 302 sq ft | 3 | 2 |
| 1 BHK | 29.46 sq m · 317 sq ft | 3 | 1 |
| 1 RK WITH TERRACE | 17.44 sq m · 188 sq ft | 1 | 0 |
| 1 RK WITH TERRACE | 19.37 sq m · 208 sq ft | 1 | 0 |
| 1 RK WITH TERRACE | 19.37 sq m · 208 sq ft | 1 | 1 |
Show all 13 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 RK WITH TERRACE | 21.61 sq m · 233 sq ft | 1 | 1 |
| Shop no 1 | 9.31 sq m · 100 sq ft | 1 | 0 |
| Shop no 2 | 10.82 sq m · 116 sq ft | 1 | 0 |
| Shop no 3 | 14.01 sq m · 151 sq ft | 1 | 0 |
| Shop no 4 | 13.79 sq m · 148 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals1
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Triarch Design Studio | — |
Source: MahaRERA project page. Contact details are not shown.