Tanzanite

Completion was pushed back 4 months, to Apr 2030; no MahaRERA orders on record; 2% of its units are booked.

Mamdapur, Raigarh 410101 · Promoter: Kohinoor Developers

DeliveryExtended 4 moPromised Dec 2029 · now due Apr 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales2% booked1 of 42 units · as the promoter reported to MahaRERA
Tanzanite project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 4 months, to Apr 2030

  • This projectRegistered 31 May 2024, completion promised 31 Dec 2029, revised to 30 Apr 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000056373
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005637331 May 202431 Dec 202930 Apr 2030Kohinoor DevelopersProject page
Documents62

1 document held by Deedo, 61 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 3 May 2024Source

Legal

  • Declaration Form BForm B.pdf · uploaded 4 May 2024Source
  • Other – Legalkharedikat 1.pdf · uploaded 9 May 2024Source
  • Other – Legalkharedikat 2.pdf · uploaded 9 May 2024Source
  • Other – LegalPARTNERSHIP DEED.pdf · uploaded 9 May 2024Source
  • Legal Title reportTitle Report.pdf · uploaded 9 May 2024Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 3 May 2024Source
Show all 62 documentsShow fewer documents

Migrated

  • 1 a Details of encumbrances concerned to FinanceNo encumbrances Certificate FINANCE and LEGAL.pdf · uploaded 4 May 2024Source
  • 1 b Details of encumbrances concerned to LegalNo encumbrances Certificate FINANCE and LEGAL.pdf · uploaded 4 May 2024Source
  • 1 Copy of Layout Approval (in case of layout)PLAN - converted.pdf · uploaded 4 May 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentPLAN - converted.pdf · uploaded 4 May 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMM CERT - converted.pdf · uploaded 4 May 2024Source
  • 1 Declaration about Commencement Certificatedeclaration about comm cert.pdf · uploaded 4 May 2024Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 4 May 2024Source
  • 1 CERSAI detailsCersai_Declaration.pdf · uploaded 4 May 2024Source
  • 1 Proforma of Allotment letterALLOTMENT DRAFT.pdf · uploaded 4 May 2024Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 4 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A bank account decla (7).pdf · uploaded 4 May 2024Source
  • 1 Deviation Report with respect to Allotment letterdeviation-allotment.pdf · uploaded 4 May 2024Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation-draft sale.pdf · uploaded 4 May 2024Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 9 May 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclouser of Interest in other real estate.pdf · uploaded 9 May 2024Source
  • 1 Other – Legalkharedikat 1.pdf · uploaded 9 May 2024Source
  • 2 Other – Legalkharedikat 2.pdf · uploaded 9 May 2024Source
  • 3 Other – LegalPARTNERSHIP DEED.pdf · uploaded 9 May 2024Source
  • 1 Other – TechnicalANNEXURE -A.pdf · uploaded 9 May 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentdeclaration about comm cert new.pdf · uploaded 25 May 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Dec 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 25 Dec 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 converted.pdf · uploaded 25 Dec 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30-09 - converted.pdf · uploaded 25 Dec 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Dec 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 17 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 17 Feb 2025Source
  • Withdrawal Update Form 1Form 1 30-06-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 1Form 1 30-09-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 1Form 1 31-12-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form 2 30-06-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form 2 30-09-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Form 2 31-12-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3Form 3 30-06-2025 KOHINNOR.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3Form 3 30-09-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3Form 3 31-12-25.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 1KONINOOR - Form 1 Architect Form - RERA - 31-03-26.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 2KOHINOOR -Form 2 Engineer Form - RERA-31-03-26.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 3Form 3 31-03-26 KOHINNOR.pdf · uploaded 30 May 2026Source
  • Withdrawal Update Form 1KONINOOR - Form 1 Architect Form - RERA - 31-03-26.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 2KOHINOOR -Form 2 Engineer Form - RERA-31-03-26.pdf · uploaded 22 Jul 2026Source
  • Withdrawal Update Form 3Form 3 kohinoor Developers 30-06-2026.pdf · uploaded 22 Jul 2026Source

Technical

  • DocumentPLAN - converted.pdf · uploaded 4 May 2024Source
  • DocumentPLAN - converted.pdf · uploaded 4 May 2024Source
  • Other – TechnicalANNEXURE -A.pdf · uploaded 9 May 2024Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 25 Dec 2024Source
  • DocumentForm 1.pdf · uploaded 25 Dec 2024Source
  • DocumentKONINOOR - Form 1 Architect Form - RERA - 31-03-26.pdf · uploaded 30 May 2026Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 25 Dec 2024Source
  • DocumentForm 2.pdf · uploaded 25 Dec 2024Source
  • DocumentKOHINOOR -Form 2 Engineer Form - RERA-31-03-26.pdf · uploaded 30 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPlot no 10 Survey no 175

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK42 units in all
Address
Plot no 10 Survey no 175, Karjat, MamdapurPIN 410101
Village
Mamdapur, Karjat taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot no 10 Survey no 175

Boundaries

North
Road
South
Plot No 11 and 9
East
Plot no 8
West
Plot no 13

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking42 units

1 of 42 units booked (2%), as the promoter reported to MahaRERA

1BHK · 42 units
TypeCarpet areaUnitsBooked
1BHK34.13 sq m · 367 sq ft361
1BHK39.95 sq m · 430 sq ft60

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHorizon Consultancy—
Chartered accountantManish K Ramawati And Company—
EngineerFaiz palte—
EngineerHorizon Consultancy—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology