Its promised completion date, Jan 2019, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 8% of its units are booked.

Karanjade, Raigarh 410206 · Promoter: Rushi Developers

Delivery7 yrs 9 mo past duePromised Jan 2019 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales8% booked1 of 12 units · as the promoter reported to MahaRERA
Rushikesh project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Jan 2019, has passed and MahaRERA does not show it completed

  • This projectRegistered 11 Aug 2017, completion promised 31 Jan 2019, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000005675
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000567511 Aug 201731 Jan 201931 Jan 2019Rushi DevelopersProject page
Documents20

1 document held by Deedo, 19 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Declaration Form BFORM B.pdf · uploaded 31 Jul 2017Source
  • Legal Title reportTITLE REPORT.pdf · uploaded 31 Jul 2017Source

Migrated

  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 31 Jul 2017Source
  • 1 Details of encumbrancesENCUMBRANCES CERT.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)APPROVAL PLAN.pdf · uploaded 31 Jul 2017Source
  • 1 Building Plan Approval (IOD)APPROVAL PLAN.pdf · uploaded 31 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentIODCC.pdf · uploaded 31 Jul 2017Source
Show all 20 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BFORM B.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH CERT.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG CERT.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA CERT 3.pdf · uploaded 31 Jul 2017Source
  • 1 Proforma of Allotment letterAGGREMENT FOR SALE.pdf · uploaded 31 Jul 2017Source
  • 2 Proforma of Allotment letterLETTER OF ALLOTMENT.pdf · uploaded 31 Jul 2017Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC 54.pdf · uploaded 4 Mar 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 4 Mar 2020Source

Technical

  • DocumentAPPROVAL PLAN.pdf · uploaded 31 Jul 2017Source
  • DocumentAPPROVAL PLAN.pdf · uploaded 31 Jul 2017Source

Technical (Architect)

  • DocumentARCH CERT.pdf · uploaded 31 Jul 2017Source

Technical (Engineer)

  • DocumentENG CERT.pdf · uploaded 31 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsSECTOR 2A PLOT 54

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1 BHK, 1 RK, 1RK, 1RK TERRACE12 units in all
Address
Sector 2a Plot 54PIN 410206
Village
Karanjade, Panvel taluka
Designated bank account
28
Developed in phases
No

Survey, CTS, gat or plot numbers

SECTOR 2A PLOT 54

Boundaries

North
Plot 57 And 58
South
9 Mtr Wide Road
East
Plot No 55
West
Plot No 53

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking12 units

1 of 12 units booked (8%), as the promoter reported to MahaRERA

1 BHK · 3 units1 RK · 2 units1RK · 6 units1RK TERRACE · 1 unit
TypeCarpet areaUnitsBooked
1 BHK21.56 sq m · 232 sq ft31
1 RK13.2 sq m · 142 sq ft20
1RK14.15 sq m · 152 sq ft60
1RK TERRACE18.75 sq m · 202 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals2

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel Architects—
EngineerS R Consultants—

Source: MahaRERA project page. Contact details are not shown.