Janaki
Deedo IDDP-RAI-A7RVIts promised completion date, Jun 2023, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 0% of its units are booked.
Karanjade, Raigarh 410206 · Promoter: Four Dimensional Spaces
Its promised completion date, Jun 2023, has passed and MahaRERA does not show it completed
- This projectRegistered 4 Jul 2020, completion promised 30 Jun 2023, and still not shown completed today.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000025717
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000025717 | 4 Jul 2020 | 30 Jun 2023 | 30 Jun 2023 | Four Dimensional Spaces | Project page |
Documents28
1 document held by Deedo, 27 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card (2).pdf · uploaded 2 Jul 2020Source
Legal
Migrated
- 1 Copy of Layout Approval (in case of layout)Approved Building Layout.pdf · uploaded 15 Jun 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentApproved Building Layout.pdf · uploaded 15 Jun 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCIDCO CC - FDS.pdf · uploaded 15 Jun 2020Source
Show all 28 documentsShow fewer documents
Migrated
- 1 Proforma of Allotment letterPROFORMA SALE AGREEMENT.pdf · uploaded 15 Jun 2020Source
- 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 15 Jun 2020Source
- 1 Copy of the legal title reportSEARCH REPORT (2).pdf · uploaded 17 Jun 2020Source
- 2 Copy of the legal title reportCLEARANCE CERTIFICATE (2).pdf · uploaded 17 Jun 2020Source
- 1 Details of encumbrancesSEARCH REPORT (2).pdf · uploaded 17 Jun 2020Source
- 2 Details of encumbrancesCLEARANCE CERTIFICATE (2).pdf · uploaded 17 Jun 2020Source
- 1 Declaration in FORM BFrom B Notarized.pdf · uploaded 22 Jun 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate (3).pdf · uploaded 26 Jun 2020Source
- 1 PAN CardPAN Card (2).pdf · uploaded 2 Jul 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 2020-21.pdf · uploaded 19 Feb 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 2021-22.pdf · uploaded 19 Feb 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Declaration Format A.pdf · uploaded 19 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31 march 2021.pdf · uploaded 4 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31 March 2022.pdf · uploaded 4 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31 March 2023.pdf · uploaded 4 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 FY 2022-23.pdf · uploaded 4 Jan 2024Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC_0001.pdf · uploaded 10 Feb 2024Source
- 1 Architect’s Certificate on Completion of Project (Form 4)form 4.pdf · uploaded 10 Feb 2024Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPLOT NO 68
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1RK, Shop17 units in all
- Address
- Plot No 68, Sector No 4, Karanjade (New)PIN 410206
- Village
- Karanjade, Panvel taluka
- Designated bank account
- 212
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 56
- South
- Plot No 67
- East
- Plot No 69
- West
- 7 Mtr Road
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking17 units
0 of 17 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 22.47 sq m · 242 sq ft | 3 | 0 |
| 1BHK | 22.73 sq m · 245 sq ft | 3 | 0 |
| 1BHK | 23.14 sq m · 249 sq ft | 1 | 0 |
| 1RK | 17.27 sq m · 186 sq ft | 1 | 0 |
| 1RK | 19.47 sq m · 210 sq ft | 7 | 0 |
| Shop | 11.61 sq m · 125 sq ft | 1 | 0 |
| Shop | 11.79 sq m · 127 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Entity Architects | — |
| Chartered accountant | Ajinkya Vaishampayan | — |
| Engineer | Vastukalp | — |
Source: MahaRERA project page. Contact details are not shown.