Blue Crest

Its promised completion date, Dec 2018, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 79% of its units are booked.

Karanjade, Raigarh 410206 · Promoter: Elinor Infra LLP

Delivery7 yrs 10 mo past duePromised Dec 2018 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales79% booked70 of 89 units · as the promoter reported to MahaRERA
Blue Crest project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Dec 2018, has passed and MahaRERA does not show it completed

  • This projectRegistered 22 Aug 2017, completion promised 31 Dec 2018, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000009702
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200000970222 Aug 201731 Dec 201831 Dec 2018Elinor Infra LLPProject page
Documents44

1 document held by Deedo, 43 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardELINOR INFRA PAN CARD.pdf · uploaded 27 Jul 2017Source

Legal

  • Legal Title reportTitle report 2.pdf · uploaded 27 Jul 2017Source
  • Declaration Form BForm B Affidavit.pdf · uploaded 28 Jul 2017Source
  • OtherOCC.pdf · uploaded 3 Dec 2018Source

Migrated

  • 1 PAN CardELINOR INFRA PAN CARD.pdf · uploaded 27 Jul 2017Source
  • 1 Copy of the legal title reportTitle report 2.pdf · uploaded 27 Jul 2017Source
  • 1 Details of encumbrancesencumbrance certificate.pdf · uploaded 28 Jul 2017Source
Show all 44 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Plan1.pdf · uploaded 28 Jul 2017Source
  • 2 Copy of Layout Approval (in case of layout)Plan2.pdf · uploaded 28 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)Plan3.pdf · uploaded 28 Jul 2017Source
  • 4 Copy of Layout Approval (in case of layout)Plan4.pdf · uploaded 28 Jul 2017Source
  • 5 Copy of Layout Approval (in case of layout)Plan5.pdf · uploaded 28 Jul 2017Source
  • 6 Copy of Layout Approval (in case of layout)Plan6.pdf · uploaded 28 Jul 2017Source
  • 7 Copy of Layout Approval (in case of layout)Plan7.pdf · uploaded 28 Jul 2017Source
  • 8 Copy of Layout Approval (in case of layout)Plan8.pdf · uploaded 28 Jul 2017Source
  • 1 Building Plan Approval (IOD)cidco 1 set Elinor infra llpmin.pdf · uploaded 28 Jul 2017Source
  • 2 Building Plan Approval (IOD)cidco 3 set Elinor infra llpmin.pdf · uploaded 28 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentcidco 1 set Elinor infra llpmin.pdf · uploaded 28 Jul 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentcidco 3 set Elinor infra llpmin.pdf · uploaded 28 Jul 2017Source
  • 1 Declaration in FORM BForm B Affidavit.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect's certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Pawan Chaurasia -eng certificate.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)ELINOR INFRA LLP07282017 01.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterDeclaration for Allotment letter and Sale Agreement.pdf · uploaded 28 Jul 2017Source
  • 2 Proforma of Allotment letterAgreement for sale.pdf · uploaded 14 Nov 2017Source
  • 3 Proforma of Allotment letterLATEST FORMAT AGREEMENT FOR SALE.pdf · uploaded 14 Nov 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate - Elinor Infra LLP.pdf · uploaded 16 Nov 2017Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate.pdf · uploaded 16 Nov 2017Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Rajesh Architect - certificate.pdf · uploaded 30 Mar 2018Source
  • 1 Certificates of Architect (Form 4)Form 4 Rajesh RC Certificate -elinor INfra LL P.pdf · uploaded 3 Dec 2018Source
  • 1 OtherOCC.pdf · uploaded 3 Dec 2018Source

Technical

  • DocumentPlan2.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan3.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan4.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan7.pdf · uploaded 28 Jul 2017Source
  • Documentcidco 1 set Elinor infra llpmin.pdf · uploaded 28 Jul 2017Source
  • Documentcidco 3 set Elinor infra llpmin.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan8.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan6.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan1.pdf · uploaded 28 Jul 2017Source
  • DocumentPlan5.pdf · uploaded 28 Jul 2017Source

Technical (Architect)

  • DocumentRajesh Architect - certificate.pdf · uploaded 30 Mar 2018Source

Technical (Engineer)

  • Documentengineer certificate.pdf · uploaded 16 Nov 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPlot No. 93

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Unit types
Residential, Shop89 units in all
Address
Plot No. 93PIN 410206
Village
Karanjade, Panvel taluka
Designated bank account
51
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No. 93

Boundaries

North
Plot No A-107
South
Plot No - 92
East
Plot No A-105
West
15m Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking89 units

70 of 89 units booked (79%), as the promoter reported to MahaRERA

Residential · 82 unitsShop · 7 units
TypeCarpet areaUnitsBooked
Residential25.53 sq m · 275 sq ft11
Residential47.18 sq m · 508 sq ft21
Residential50.87 sq m · 548 sq ft22
Residential105.2 sq m · 1,132 sq ft33
Residential106.09 sq m · 1,142 sq ft33
Residential131.06 sq m · 1,411 sq ft33
Residential131.08 sq m · 1,411 sq ft32
Residential151.97 sq m · 1,636 sq ft66
Show all 21 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Residential259.1 sq m · 2,789 sq ft87
Residential262.06 sq m · 2,821 sq ft87
Residential262.81 sq m · 2,829 sq ft97
Residential320.04 sq m · 3,445 sq ft93
Residential320.12 sq m · 3,446 sq ft96
Residential426.96 sq m · 4,596 sq ft1616
Shop17.38 sq m · 187 sq ft10
Shop17.75 sq m · 191 sq ft10
Shop17.81 sq m · 192 sq ft10
Shop18.2 sq m · 196 sq ft11
Shop18.63 sq m · 201 sq ft11
Shop18.82 sq m · 203 sq ft11
Shop20.89 sq m · 225 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRajesh R C—
EngineerPawan Chaurasiya—
Registered real estate agentSpace India Builders & Developers—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology