Aikyam Two
Completion was pushed back 4 months, to Oct 2029; no MahaRERA orders on record; 0% of its units are booked.
Dapoli, Raigarh 410206 · Promoter: Today Royal Housing
Completion was pushed back 4 months, to Oct 2029
- This projectRegistered 23 Apr 2025, completion promised 30 Jun 2029, revised to 30 Oct 2029.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000080085
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000080085 | 23 Apr 2025 | 30 Jun 2029 | 30 Oct 2029 | Today Royal Housing | Project page |
Documents73
1 document held by Deedo, 72 filings listed on MahaRERA's project page
Finance
Legal
- Declaration Form BFORM -B Promoter.pdf · uploaded 4 Feb 2025Source
- Legal Title reportShort Title.pdf · uploaded 14 Feb 2025Source
- Other – LegalLEASE DEED 1-50.pdf · uploaded 4 Apr 2025Source
- Other – LegalLEASE DEED - 51-80.pdf · uploaded 4 Apr 2025Source
- Other – LegalLEASE DEED - 81-110.pdf · uploaded 4 Apr 2025Source
Show all 73 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardFirm Pan.pdf · uploaded 3 Feb 2025Source
- 1 a Details of encumbrances concerned to FinanceNo Encumbrance Letter -Dues.pdf · uploaded 4 Feb 2025Source
- 1 Declaration in FORM BFORM -B Promoter.pdf · uploaded 4 Feb 2025Source
- 1 b Details of encumbrances concerned to LegalNo Encumbrance Letter -Dues.pdf · uploaded 4 Feb 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 4 Feb 2025Source
- 1 Disclosure for secured/unsecured finance availed for the projectDisclosure for secured and unsecured finance availed for the project.pdf · uploaded 4 Feb 2025Source
- 2 a Details of encumbrances concerned to FinanceNo Encumbrance Letter - Litigations.pdf · uploaded 6 Feb 2025Source
- 1 CERSAI detailsDeclaration of Cersai.pdf · uploaded 6 Feb 2025Source
- 2 b Details of encumbrances concerned to LegalNo Encumbrance Letter - Litigations.pdf · uploaded 6 Feb 2025Source
- 1 Other – Technical1 Other – Technical (3) (1).pdf · uploaded 6 Feb 2025Source
- 1 Copy of the legal title reportShort Title.pdf · uploaded 14 Feb 2025Source
- 1 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 4 Apr 2025Source
- 1 Proforma of Allotment letterAllotement Aikyam.pdf · uploaded 4 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 4 Apr 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 4 Apr 2025Source
- 2 Commencement Certificates / NA Order for plotted developmentCC Verification.pdf · uploaded 4 Apr 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan 1-3.pdf · uploaded 4 Apr 2025Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan 4-7.pdf · uploaded 4 Apr 2025Source
- 5 Other – Legal1-50.pdf · uploaded 4 Apr 2025Source
- 7 Other – LegalTripartite - 06-12-2024.pdf · uploaded 4 Apr 2025Source
- 6 Other – Legal51-90.pdf · uploaded 4 Apr 2025Source
- 3 Other – LegalLEASE DEED - 81-110.pdf · uploaded 4 Apr 2025Source
- 2 Other – LegalLEASE DEED - 51-80.pdf · uploaded 4 Apr 2025Source
- 1 Other – LegalLEASE DEED 1-50.pdf · uploaded 4 Apr 2025Source
- 4 Other – LegalLEASE DEED - 111-142.pdf · uploaded 4 Apr 2025Source
- 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 4 Apr 2025Source
- 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A-.pdf · uploaded 4 Apr 2025Source
- 1 Deviation Report with respect to Allotment letterDeviation Report for Allotment.pdf · uploaded 4 Apr 2025Source
- 2 Other – TechnicalCC Verification.pdf · uploaded 4 Apr 2025Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report for AFS.pdf · uploaded 4 Apr 2025Source
- 1 Proforma of Agreement for saleAFS.pdf · uploaded 4 Apr 2025Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsPower of Attorney - Company.pdf · uploaded 4 Apr 2025Source
- 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 4 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Declaration for Estimated cost.pdf · uploaded 11 Apr 2025Source
- 1 Other – FinanceDeclaration for Estimated cost.pdf · uploaded 17 Apr 2025Source
- Withdrawal Update Form 1Form 1 - Aikyam Two as on June 2025.pdf · uploaded 2 Sep 2025Source
- Withdrawal Update Form 2Form 2 - Aikyam Two as on June 2025.pdf · uploaded 2 Sep 2025Source
- Withdrawal Update Form 3Form 3 - Aikyam Two as on June 2025.pdf · uploaded 2 Sep 2025Source
- Withdrawal Update Form 1Form 1 - Aikyam Two as on Sept 2025.pdf · uploaded 13 Nov 2025Source
- Withdrawal Update Form 2Form 2 - Aikyam Two as on Sept 2025.pdf · uploaded 13 Nov 2025Source
- Withdrawal Update Form 3Form 3 - Aikyam Two as on Sept 2025.pdf · uploaded 13 Nov 2025Source
- Withdrawal Update Form 1Form 1 - Aikyam Two as on Dec 2025.pdf · uploaded 14 Feb 2026Source
- Withdrawal Update Form 2Form 2 - Aikyam Two as on Dec 2025.pdf · uploaded 14 Feb 2026Source
- Withdrawal Update Form 3Form 3 - Aikyam Two as on Dec 2025.pdf · uploaded 14 Feb 2026Source
- Withdrawal Update Form 1Form 1 - Aikyam Two as on 31-03-26.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 2Form 2 - Aikyam Two as on 31-03-26.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 3Form 3 - Aikyam Two as on 31-03-26.pdf · uploaded 12 May 2026Source
- Withdrawal Update Form 1FORM 1 ARCHITECT CERTIFICATE 2026-06-30 (1)- Aikyam Two.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 2Aikyam_Two_Form2_Q1_2026-27_20-07-2026_07-27.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 3Aikyam_Two_Form3_Q1_2026-27_18-07-2026_13-40_doc1.pdf · uploaded 20 Jul 2026Source
- Withdrawal Update Form 1FORM 1 ARCHITECT CERTIFICATE 2026-06-30 (1)- Aikyam Two.pdf · uploaded 3 Sep 2026Source
- Withdrawal Update Form 2Aikyam_Two_Form2_Q1_2026-27_20-07-2026_07-27.pdf · uploaded 3 Sep 2026Source
- Withdrawal Update Form 3Aikyam_Two_Form3_Q1_2026-27_18-07-2026_13-40_doc1.pdf · uploaded 3 Sep 2026Source
- Form 5 (FY 2025-2026)Form 5 - Aikyam Two Fy 25-26.pdf · uploaded 30 Sep 2026Source
Technical
Technical (Architect)
- DocumentFORM 1 ARCHITECT CERTIFICATE 2026-06-30 (1)- Aikyam Two.pdf · uploaded 20 Jul 2026Source
Technical (Engineer)
- DocumentAikyam_Two_Form2_Q1_2026-27_20-07-2026_07-27.pdf · uploaded 20 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsPlot No. 25, Sector No. 4
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK, Duplex Shop180 units in all
- Address
- Plot No. 25, Sector No. 4, PushpakPIN 410206
- Village
- Dapoli, Panvel taluka
- Location
- 18.97560, 73.07866
- Designated bank account
- 76
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 26
- South
- Plot No 3B 24 24A and 24B
- East
- 20 Mtrs Wide Road
- West
- Plot No 2
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking180 units
0 of 180 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.22 sq m · 368 sq ft | 22 | 0 |
| 2BHK | 47.24 sq m · 508 sq ft | 20 | 0 |
| 2BHK | 49.84 sq m · 536 sq ft | 38 | 0 |
| 2BHK | 50.01 sq m · 538 sq ft | 18 | 0 |
| 2BHK | 50.48 sq m · 543 sq ft | 4 | 0 |
| 2BHK | 50.65 sq m · 545 sq ft | 4 | 0 |
| 2BHK | 54.97 sq m · 592 sq ft | 11 | 0 |
| 2BHK | 54.98 sq m · 592 sq ft | 11 | 0 |
Show all 17 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 56.02 sq m · 603 sq ft | 22 | 0 |
| 2BHK | 57.41 sq m · 618 sq ft | 22 | 0 |
| Duplex Shop | 65.69 sq m · 707 sq ft | 1 | 0 |
| Duplex Shop | 74.42 sq m · 801 sq ft | 1 | 0 |
| Duplex Shop | 74.58 sq m · 803 sq ft | 2 | 0 |
| Duplex Shop | 85.73 sq m · 923 sq ft | 1 | 0 |
| Duplex Shop | 92.8 sq m · 999 sq ft | 1 | 0 |
| Duplex Shop | 111.62 sq m · 1,201 sq ft | 1 | 0 |
| Duplex Shop | 152.08 sq m · 1,637 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Destination Architecture Interior Designs | — |
| Chartered accountant | N B Sayed & Associates | — |
| Engineer | Aadhar Engineers Structural Designers & Project Consultants | — |
Source: MahaRERA project page. Contact details are not shown.