One Talegaon
Deedo IDDP-PUN-WN2CCompletion was pushed back 4 months, to Jul 2028; no MahaRERA orders on record.
Varale, Pune 410507 · Promoter: Iprima Infra LLP
Completion was pushed back 4 months, to Jul 2028
- This projectRegistered 13 Aug 2025, completion promised 31 Mar 2028, revised to 31 Jul 2028.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationPP1260002500563
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PP1260002500563 | 13 Aug 2025 | 31 Mar 2028 | 31 Jul 2028 | Iprima Infra LLP | Project page |
Documents41
1 document held by Deedo, 40 filings listed on MahaRERA's project page
Finance
- OthersEncumbrances-Finance-One Talegaon.pdf · uploaded 6 Aug 2025Source
- OthersClarification-Reason for mortgage not reflectiong in CERSAI 04082025.pdf · uploaded 6 Aug 2025Source
- PAN CardPAN-Iprima Infra LLP.pdf · uploaded 6 Aug 2025Source
- OthersCA Letter-Fund Utilization (UDIN) 04082025.pdf · uploaded 12 Aug 2025Source
Show all 41 documentsShow fewer documents
Legal
- Declaration Form BPower Of Attorney 16102024.pdf · uploaded 4 Aug 2025Source
- OthersDisclosure of Interest-Dhanesh Sancheti 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDisclosure of Interest-Fanindra Gujar (Biz Vert) 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDisclosure of Interest-Gunesh Sancheti 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDisclosure of Interest-Pratik Doshi (Biz Vert) 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDisclosure of Interest-Rutuj Mutha 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDisclosure of Interest-Sheetal Sancheti 04082025.pdf · uploaded 6 Aug 2025Source
- OthersEncumbrances-Legal-One Talegaon 04082025.pdf · uploaded 6 Aug 2025Source
- Declaration Form B7-12 Extracts (103 Plots)-Combined.pdf · uploaded 6 Aug 2025Source
- OthersDeclaration of Gat No -One Talegaon.pdf · uploaded 12 Aug 2025Source
- Declaration Form BLegal Title Report One Talegaon 12082025.pdf · uploaded 12 Aug 2025Source
- OthersSale Deed (After AFS) 20112025 -Final.pdf · uploaded 5 Dec 2025Source
Migrated
- Withdrawal Update Form 1Form-1 Architect Certificate 30122025.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 1Form-1 Architect Certificate 30092025.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 2Form-2 Engineer Certificate-One Talegaon 31122025.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 2Form-2 Engineer Certificate-One Talegaon 30092025.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 3Withdrawal Application Form-3 31122025.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 3Withdrawal Application Form-3 30092025.pdf · uploaded 21 Mar 2026Source
- Withdrawal Update Form 1Form-2 Engineer Certificate 31032026.pdf · uploaded 10 Jun 2026Source
- Withdrawal Update Form 2Form-2 Engineer Certificate 31032026.pdf · uploaded 10 Jun 2026Source
- Withdrawal Update Form 3Form-3 CA Certificate 31032026.pdf · uploaded 10 Jun 2026Source
Technical
- DocumentNA Order 23092024.pdf · uploaded 5 Aug 2025Source
- DocumentSanction Plan -1-4 19062024.pdf · uploaded 6 Aug 2025Source
- DocumentSanction Plan -2-4 19062024.pdf · uploaded 6 Aug 2025Source
- DocumentSanction Plan -3-4 19062024.pdf · uploaded 6 Aug 2025Source
- DocumentSanction Plan -4-4 19062024.pdf · uploaded 6 Aug 2025Source
- DocumentAnnexure-A Declaration-Cum-Undertaking-One Talegaon 06082025.pdf · uploaded 6 Aug 2025Source
- OthersForm-1 Architect Certificate-One Talegaon.pdf · uploaded 6 Aug 2025Source
- OthersLetter-D3 Clarification-One Talegaon 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDeclaration-Land Area & Plot No-One Talegaon 04082025.pdf · uploaded 6 Aug 2025Source
- OthersDeclaration For 8 Plots excluded 08082025.pdf · uploaded 12 Aug 2025Source
Technical (Architect)
- DocumentForm-2 Engineer Certificate 31032026.pdf · uploaded 10 Jun 2026Source
Technical (Engineer)
- DocumentForm-2 Engineer Certificate 31032026.pdf · uploaded 10 Jun 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals62, Gat No 61
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- Mouje-VaralePIN 410507
- Village
- Varale, Mawal taluka
- Location
- 18.74265, 73.66961
- Designated bank account
- 43
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- Proposed 18.00 M DP Road
- South
- 15 M wide Existing Road
- East
- Adjoining Gat No. 60
- West
- Shifted TP Reservation No. 34 and Amenity Space
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Milind Saraf | — |
| Chartered accountant | Priyesh Prakash Jain | — |
| Engineer | Nimish Lakhari | — |
Source: MahaRERA project page. Contact details are not shown.