Completed12 floorsRERA P52100000011
Yashwin Jeevan A, Yashwin Jeevan
MahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Completion30 Apr 2018as registered
Units & parking in Yashwin Jeevan A
MahaRERA's project page with unit types hasn't been imported for this registration.
Parking: Closed/Covered 17 · Open Space 8 (as declared to MahaRERA)
Construction progress (declared)
Work completed, as the promoter reported it to MahaRERA (Form 1). Not verified on site.
- Excavation100%
- Basement (if any)100%
- Podiums (if any)0%
- Plinth100%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
As registered with MahaRERA
- Sanctioned habitable floors
- 12
- Deedo ID
- BLD_013572
Questions about Yashwin Jeevan A
When is Yashwin Jeevan A due for completion?
The MahaRERA registration promises 30 Apr 2018.
How many floors does Yashwin Jeevan A have?
12 sanctioned habitable floors, as registered with MahaRERA.
Data through12 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology