Residential / Group Housing · 6 buildings · 701 unitsRERA P52100031556

VTP Verve

Completion was pushed back 3 years and 6 months, to Dec 2029; 1 listing or order with MahaRERA on record; 84% of its units are booked.

Sus, Pune 411045 · Promoter: Prasanna Developers

DeliveryExtended 3 yrs 6 moPromised Jun 2026 · now due Dec 2029Regulatory1 listing or orderLatest: Regulatory order, 2025Sales84% booked589 of 701 units · as the promoter reported to MahaRERA
VTP Verve project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 3 years and 6 months, to Dec 2029

  • This projectRegistered 28 Oct 2021, completion promised 30 Jun 2026, revised to 31 Dec 2029.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

6 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory record1

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order19 May 2025Matched by RERA number

    Regulatory order: PROJECT NAME: VTP VERVE (Regulatory Case No. 365 OF 2025) dated 19 May, 2025.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100031556
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003155628 Oct 202130 Jun 202631 Dec 2029Prasanna DevelopersProject page
Documents153

2 documents held by Deedo, 151 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN Card1 PAN Card.pdf · uploaded 4 Mar 2025Source

Legal

  • Legal Title reportFormat A Title Report.pdf · uploaded 18 Oct 2021Source
  • Legal Title reportFinal TR.pdf · uploaded 18 Oct 2021Source
  • Declaration Form BFORM B.pdf · uploaded 18 Oct 2021Source

Migrated

  • 1 Copy of the legal title reportFormat A Title Report.pdf · uploaded 18 Oct 2021Source
  • 2 Copy of the legal title reportFinal TR.pdf · uploaded 18 Oct 2021Source
Show all 153 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrance_Verve.pdf · uploaded 18 Oct 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 18 Oct 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout.pdf · uploaded 18 Oct 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 18 Oct 2021Source
  • 1 Declaration about Commencement Certificateformt D.pdf · uploaded 18 Oct 2021Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 18 Oct 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 18 Oct 2021Source
  • 1 Proforma of Allotment letterAP.pdf · uploaded 18 Oct 2021Source
  • 2 Proforma of Allotment letter1.pdf · uploaded 18 Oct 2021Source
  • 3 Proforma of Allotment letter2.pdf · uploaded 18 Oct 2021Source
  • 4 Proforma of Allotment letter3.pdf · uploaded 18 Oct 2021Source
  • 5 Proforma of Allotment letter4.pdf · uploaded 18 Oct 2021Source
  • 6 Proforma of Allotment letter5.pdf · uploaded 18 Oct 2021Source
  • 7 Proforma of Allotment letter6.pdf · uploaded 18 Oct 2021Source
  • 8 Proforma of Allotment letter7.pdf · uploaded 18 Oct 2021Source
  • 9 Proforma of Allotment letter8.pdf · uploaded 18 Oct 2021Source
  • 10 Proforma of Allotment letter9.pdf · uploaded 18 Oct 2021Source
  • 11 Proforma of Allotment letter10.pdf · uploaded 18 Oct 2021Source
  • 1 Disclosure of sold/ booked inventoryVerve.pdf · uploaded 10 Feb 2022Source
  • 2 Disclosure of sold/ booked inventoryVerve.pdf · uploaded 11 Apr 2022Source
  • 1 CERSAI detailsVerve.pdf · uploaded 14 Apr 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Verve.pdf · uploaded 19 Apr 2022Source
  • 3 Disclosure of sold/ booked inventoryVerve_compressed.pdf · uploaded 7 Jul 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Verve_compressed.pdf · uploaded 20 Jul 2022Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 - VERVE -.pdf · uploaded 28 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 VERVE 21 22.pdf · uploaded 1 Mar 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 30092022.pdf · uploaded 10 Mar 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 31122022.pdf · uploaded 24 Mar 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)VTP VERVE FORM 2.pdf · uploaded 25 Mar 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 31032022.pdf · uploaded 28 Mar 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 31122021_compressed.pdf · uploaded 28 Mar 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Verve 31032023.pdf · uploaded 29 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A VERVE 31032022.pdf · uploaded 26 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A VERVE 31032023.pdf · uploaded 26 Jul 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 30062023.pdf · uploaded 1 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 31032023_removed_compressed.pdf · uploaded 1 Aug 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 30062023_compressed.pdf · uploaded 19 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 31032023.pdf · uploaded 24 Aug 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)VERVE JUNE-23.pdf · uploaded 24 Aug 2023Source
  • 4 Disclosure of sold/ booked inventoryVERVE 30092022.pdf · uploaded 13 Sep 2023Source
  • 5 Disclosure of sold/ booked inventoryVERVE 31122022.pdf · uploaded 13 Sep 2023Source
  • 6 Disclosure of sold/ booked inventoryVERVE 31032023.pdf · uploaded 13 Sep 2023Source
  • 7 Disclosure of sold/ booked inventoryVERVE 30062023.pdf · uploaded 13 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 VERVE 2022-23.pdf · uploaded 26 Sep 2023Source
  • 2 Details of encumbrancesVerve - FE.pdf · uploaded 17 Oct 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 30092023.pdf · uploaded 19 Oct 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 30092023.pdf · uploaded 20 Oct 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 30092023.pdf · uploaded 30 Oct 2023Source
  • 8 Disclosure of sold/ booked inventoryINVENTORY VERVE 30092023.pdf · uploaded 30 Oct 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 31122023.pdf · uploaded 22 Jan 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 31122023.pdf · uploaded 22 Jan 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 31122023.pdf · uploaded 5 Feb 2024Source
  • 9 Disclosure of sold/ booked inventoryINVENTORY VERVE 31122023.pdf · uploaded 8 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 30092022.pdf · uploaded 22 Mar 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 30092022.pdf · uploaded 22 Mar 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 31032022.pdf · uploaded 28 Mar 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 30062022.pdf · uploaded 28 Mar 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 31032022.pdf · uploaded 28 Mar 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 30062022.pdf · uploaded 28 Mar 2024Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 31032024.pdf · uploaded 4 Apr 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VERVE 31032024.pdf · uploaded 27 Apr 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 31032024.pdf · uploaded 30 Apr 2024Source
  • 10 Disclosure of sold/ booked inventoryINVENTORY VERVE 31032024.pdf · uploaded 8 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A VERVE 31032024.pdf · uploaded 16 May 2024Source
  • 2 Copy of Layout Approval (in case of layout)verve_Layout_highlighted_compressed.pdf · uploaded 5 Jul 2024Source
  • 2 Building Plan Approval / NA Order for plotted development40_54_Verve_Tower_1.pdf · uploaded 5 Jul 2024Source
  • 3 Building Plan Approval / NA Order for plotted development42_54_Verve_Tower_2.pdf · uploaded 5 Jul 2024Source
  • 4 Building Plan Approval / NA Order for plotted development44_54_Verve_T3.pdf · uploaded 5 Jul 2024Source
  • 5 Building Plan Approval / NA Order for plotted development46_54_Verve_T4.pdf · uploaded 5 Jul 2024Source
  • 6 Building Plan Approval / NA Order for plotted development48_54_Verve_T5.pdf · uploaded 5 Jul 2024Source
  • 7 Building Plan Approval / NA Order for plotted development50_54_Verve_T6.pdf · uploaded 5 Jul 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC_.pdf · uploaded 5 Jul 2024Source
  • 2 Declaration about Commencement CertificateDeclaration_CC_Verve_.pdf · uploaded 5 Jul 2024Source
  • 11 Disclosure of sold/ booked inventoryVERVE-30062024.pdf · uploaded 6 Jul 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 30062024.pdf · uploaded 27 Jul 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SIERRA PH 1VERVE 10072024.pdf · uploaded 27 Jul 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VTP VERVE 30062024.pdf · uploaded 20 Aug 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 - VERVE.pdf · uploaded 7 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryVERVE 30092024.pdf · uploaded 15 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 30092024.pdf · uploaded 16 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE10102024.pdf · uploaded 18 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)DECLARATION VERVE_rotated (1).pdf · uploaded 26 Oct 2024Source
  • 2 Declaration about all RERA Designated Bank Accounts (Format A)Format A- verve.pdf · uploaded 26 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)20241028015408.pdf · uploaded 28 Oct 2024Source
  • 3 Declaration about all RERA Designated Bank Accounts (Format A)FORMAT A VERVE.pdf · uploaded 28 Oct 2024Source
  • 4 Declaration about all RERA Designated Bank Accounts (Format A)ANNEXURE A DECLARATION CUM UNDERTAKING VTP VERVE.pdf · uploaded 28 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VTP VERVE_11zon.pdf · uploaded 30 Nov 2024Source
  • 1 Disclosure of sold/ booked inventoryVERVE 31122024.pdf · uploaded 14 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 VTP VERVE 31122024.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SIERRA PHASE 1 31122024.pdf · uploaded 29 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 VERVE 31122024.pdf · uploaded 29 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 VERVE 20012025.pdf · uploaded 29 Jan 2025Source
  • 1 PAN Card1 PAN Card.pdf · uploaded 4 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5-2021-2022_VTP VERVE.pdf · uploaded 4 Mar 2025Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5-2021-2022_VTP VERVE.pdf · uploaded 5 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Bank Letter -VTP Sierra Ph 2.pdf · uploaded 17 Mar 2025Source
  • 2 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Bank Letter VTP Verve.pdf · uploaded 17 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryVERVE 31032025.pdf · uploaded 7 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Verve 31032025.pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Verve.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Verve.pdf · uploaded 19 Apr 2025Source
  • Disclosure of Sold and Booked InventoryVERVE 31032025.pdf · uploaded 22 May 2025Source
  • Form 1Form 1 Verve 31032025.pdf · uploaded 22 May 2025Source
  • Form 2Form 2 Verve.pdf · uploaded 22 May 2025Source
  • Form 3Form 3 Verve.pdf · uploaded 22 May 2025Source
  • 1 Other – TechnicalFORM 2A VERVE.pdf · uploaded 30 Jun 2025Source
  • Form 1FORM 1 VTP VERVE.pdf · uploaded 17 Oct 2025Source
  • Form 2FORM 2 Verve old 30092025.pdf · uploaded 17 Oct 2025Source
  • Form 3FORM 3 VERVE_compressed_11zon.pdf · uploaded 17 Oct 2025Source
  • Disclosure of Sold and Booked InventoryVERVE INV.pdf · uploaded 17 Oct 2025Source
  • Form 1FORM-1 VERVE 31122025.pdf · uploaded 20 Jan 2026Source
  • Form 2FORM-2 Verve.pdf · uploaded 20 Jan 2026Source
  • Form 3FORM 3 Verve_11zon.pdf · uploaded 20 Jan 2026Source
  • Disclosure of Sold and Booked InventoryVERVE inv.pdf · uploaded 20 Jan 2026Source
  • Form 1FORM-1 VERVE.pdf · uploaded 20 Apr 2026Source
  • Form 2FORM-2 VERVE.pdf · uploaded 20 Apr 2026Source
  • Form 3FORM 3 VERVE.pdf · uploaded 20 Apr 2026Source
  • Disclosure of Sold and Booked InventoryINV VERVE 31032026.pdf · uploaded 20 Apr 2026Source
  • Form 2A (FY 2025-2026)VTP VERVE.pdf · uploaded 18 Jun 2026Source
  • Withdrawal Update Form 1FORM-1 VERVE.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 1FORM-1 VERVE.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 VTP VERVE (2).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 VTP VERVE (2).pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3FORM 3- VERVE.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3FORM 3- VERVE.pdf · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)Form 5_Prasanna Developers Verve.pdf · uploaded 24 Sep 2026Source

Technical

  • DocumentLayout.pdf · uploaded 18 Oct 2021Source
  • DocumentLayout.pdf · uploaded 18 Oct 2021Source
  • Documentverve_Layout_highlighted_compressed.pdf · uploaded 5 Jul 2024Source
  • Document40_54_Verve_Tower_1.pdf · uploaded 5 Jul 2024Source
  • Document42_54_Verve_Tower_2.pdf · uploaded 5 Jul 2024Source
  • Document44_54_Verve_T3.pdf · uploaded 5 Jul 2024Source
  • Document46_54_Verve_T4.pdf · uploaded 5 Jul 2024Source
  • Document48_54_Verve_T5.pdf · uploaded 5 Jul 2024Source
  • Document50_54_Verve_T6.pdf · uploaded 5 Jul 2024Source
  • Other – TechnicalFORM 2A VERVE.pdf · uploaded 30 Jun 2025Source

Technical (Architect)

  • DocumentFORM 1 VERVE 30092024.pdf · uploaded 16 Oct 2024Source
  • DocumentFORM 1 SIERRA PHASE 1 31122024.pdf · uploaded 29 Jan 2025Source
  • DocumentFORM 1 VERVE 31122024.pdf · uploaded 29 Jan 2025Source
  • DocumentForm 1 Verve 31032025.pdf · uploaded 19 Apr 2025Source
  • DocumentFORM-1 VERVE.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 VERVE10102024.pdf · uploaded 18 Oct 2024Source
  • DocumentFORM 2 VERVE 20012025.pdf · uploaded 29 Jan 2025Source
  • DocumentForm 2 Verve.pdf · uploaded 19 Apr 2025Source
  • DocumentFORM 2 VTP VERVE (2).pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals43/1, 44/1

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 3BHK701 units in all
Address
4(Part), 7(Part), 43/1, 44/1, 44/2, 45/1, 45/2, 46/1, 46/2, Sus Baner, SusPIN 411045
Village
Sus, Mulshi taluka
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

43/144/144/245/145/246/146/24(Part)7(Part)

Boundaries

North
Adj S No 42
South
12m wide road
East
Sno 43 Hissano 1 Part
West
Nala

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking701 units

589 of 701 units booked (84%), as the promoter reported to MahaRERA

2BHK · 468 units3BHK · 233 units
BuildingTypeCarpet areaUnitsBooked
Tower 12BHK57.87 sq m · 623 sq ft10
Tower 12BHK57.89 sq m · 623 sq ft30
Tower 12BHK60.52 sq m · 651 sq ft10
Tower 12BHK61.96 sq m · 667 sq ft10
Tower 12BHK62.27 sq m · 670 sq ft10
Tower 12BHK62.4 sq m · 672 sq ft10
Tower 22BHK70.14 sq m · 755 sq ft5558
Tower 23BHK102.96 sq m · 1,108 sq ft6026
Show all 24 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Tower 32BHK57.46 sq m · 618 sq ft2524
Tower 32BHK58.34 sq m · 628 sq ft3025
Tower 32BHK60.76 sq m · 654 sq ft3030
Tower 32BHK61.85 sq m · 666 sq ft3025
Tower 32BHK64.92 sq m · 699 sq ft3026
Tower 32BHK65.27 sq m · 703 sq ft3026
Tower 43BHK83.12 sq m · 895 sq ft5451
Tower 43BHK86.43 sq m · 930 sq ft5956
Tower 52BHK57.13 sq m · 615 sq ft2521
Tower 52BHK58.34 sq m · 628 sq ft3027
Tower 52BHK60.76 sq m · 654 sq ft3025
Tower 52BHK61.85 sq m · 666 sq ft3024
Tower 52BHK64.92 sq m · 699 sq ft3015
Tower 52BHK65.27 sq m · 703 sq ft3023
Tower 62BHK70.14 sq m · 755 sq ft5552
Tower 63BHK102.92 sq m · 1,108 sq ft6055

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals1

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerVinayak Boga—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology