Skip to content
Commercial · 1 buildingRERA P52100054398

Abhimanyu Hights

Completion was pushed back 2 years and 5 months, to Mar 2027; no MahaRERA orders on record.

Rui, Pune 413102 · Promoter: Sanjay Mahadev Choudhar

DeliveryExtended 2 yrs 5 moPromised Oct 2024 · now due Mar 2027RegulatoryNo ordersNot in any MahaRERA list or order Deedo has read
Abhimanyu Hights project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 2 years and 5 months, to Mar 2027

  • This projectRegistered 18 Jan 2024, completion promised 31 Oct 2024, revised to 31 Mar 2027.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100054398
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005439818 Jan 202431 Oct 202431 Mar 2027Sanjay Mahadev ChoudharProject page
Documents121

2 documents held by Deedo, 119 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 14 Oct 2022Source

Legal

  • Legal Title reportsearch report.pdf · uploaded 14 Oct 2022Source
  • Declaration Form Bform b (1).pdf · uploaded 21 Feb 2023Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 14 Oct 2022Source
  • 1 Copy of the legal title reportsearch report.pdf · uploaded 14 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentD.pdf · uploaded 14 Oct 2022Source
Show all 121 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate (1).pdf · uploaded 14 Oct 2022Source
  • 1 Declaration about Commencement CertificateFormat D- Abhimanyu.pdf · uploaded 14 Oct 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200249426816_For_Asset_Based_Search_12_10_2022_14_38_44_913.pdf · uploaded 14 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)E (2).pdf · uploaded 1 Nov 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 1 Nov 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate.pdf · uploaded 1 Nov 2022Source
  • 1 Proforma of Allotment lettermodel form of allotment letter.pdf · uploaded 1 Nov 2022Source
  • 1 Proforma of Agreement for sale5.pdf · uploaded 1 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterDeclaration regarding no divisions.pdf · uploaded 1 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeclaration regarding no divisions.pdf · uploaded 1 Nov 2022Source
  • 1 a Details of encumbrances concerned to Financeligal encumbrance certificate.pdf · uploaded 10 Dec 2022Source
  • 1 b Details of encumbrances concerned to Legalligal encumbrance certificate.pdf · uploaded 10 Dec 2022Source
  • 2 Proforma of Allotment letterallotment letter.pdf · uploaded 14 Dec 2022Source
  • 3 Proforma of Allotment letterMODEL OF AGGERMENT.pdf · uploaded 14 Dec 2022Source
  • 2 Deviation Report with respect to Allotment letterDeclaration regarding no divisions.pdf · uploaded 14 Dec 2022Source
  • 2 a Details of encumbrances concerned to Financeligal encumbrance certificate.pdf · uploaded 21 Feb 2023Source
  • 2 b Details of encumbrances concerned to Legalligal encumbrance certificate.pdf · uploaded 21 Feb 2023Source
  • 1 Declaration in FORM Bform b (1).pdf · uploaded 21 Feb 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsREAL ESTET.pdf · uploaded 21 Feb 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameHIGHTS (2).pdf · uploaded 27 May 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Adobe Scan 30 Nov 2023_compressed.pdf · uploaded 24 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted development2 Commencement Certificates _ NA Order for plotted development (1).pdf · uploaded 27 Dec 2023Source
  • 1 Other – Technical1 Copy of Layout Approval (in case of layout) (13).pdf · uploaded 27 Dec 2023Source
  • 2 Other – TechnicalForm 1- Abhimkanyu Hights.pdf · uploaded 27 Dec 2023Source
  • 3 Other – TechnicalForm 2- Abhimanyu.pdf · uploaded 27 Dec 2023Source
  • 4 Other – Technical2 Commencement Certificates _ NA Order for plotted development (1).pdf · uploaded 8 Jan 2024Source
  • 1 Disclosure of sold/ booked inventorySU.pdf · uploaded 16 Apr 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Engineer certificate - 1 update.pdf · uploaded 6 May 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)_Architect's Certificate update.pdf · uploaded 6 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1-JUNE-24.pdf · uploaded 16 Jan 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1-SEPT-24.pdf · uploaded 16 Jan 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1-DEC-24.pdf · uploaded 16 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1-MARCH-24.pdf · uploaded 16 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3-MARCH-24.pdf · uploaded 16 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3-JUNE-24.pdf · uploaded 16 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3-SEPT-24.pdf · uploaded 16 Jan 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3-DEC-24.pdf · uploaded 16 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2-JUNE-24.pdf · uploaded 16 Jan 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2-DEC 24.pdf · uploaded 16 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2-SEPT-24.pdf · uploaded 16 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2-MARCH-24.pdf · uploaded 16 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySU-MARCH-24.pdf · uploaded 16 Jan 2025Source
  • 2 Disclosure of sold/ booked inventorySU-JUNE-24.pdf · uploaded 16 Jan 2025Source
  • 3 Disclosure of sold/ booked inventorySU-SEPT-24.pdf · uploaded 16 Jan 2025Source
  • 4 Disclosure of sold/ booked inventorySU-DEC-24.pdf · uploaded 16 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM-2A-NEW.pdf · uploaded 16 Jan 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORAMT B-UPLOAD.pdf · uploaded 22 Jan 2025Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameIMG_0011.pdf · uploaded 25 Mar 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT-B.pdf · uploaded 25 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)F1.pdf · uploaded 20 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 20 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)F3.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 20 Apr 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 20 Apr 2025Source
  • Form 1FORM-1-MARCH-24.pdf · uploaded 28 May 2025Source
  • Form 2FORM-2-MARCH-24.pdf · uploaded 28 May 2025Source
  • Form 3F3-MARCH-24.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySU-MARCH-24.pdf · uploaded 28 May 2025Source
  • Form 1FORM-1-JUNE-24.pdf · uploaded 28 May 2025Source
  • Form 2FORM-2-JUNE-24.pdf · uploaded 28 May 2025Source
  • Form 3F3-JUNE-24.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySU-JUNE-24.pdf · uploaded 28 May 2025Source
  • Form 1FORM-1-SEPT-24.pdf · uploaded 28 May 2025Source
  • Form 2FORM-2-SEPT-24.pdf · uploaded 28 May 2025Source
  • Form 3F3-SEPT-24.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySU-SEPT-24.pdf · uploaded 28 May 2025Source
  • Form 1FORM-1-DEC-24.pdf · uploaded 28 May 2025Source
  • Form 2FORM-2-DEC 24.pdf · uploaded 28 May 2025Source
  • Form 3F3-DEC-24.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySU-DEC-24.pdf · uploaded 28 May 2025Source
  • Form 1FORM-1.pdf · uploaded 28 May 2025Source
  • Form 2FORM-2.pdf · uploaded 28 May 2025Source
  • Form 3F3.pdf · uploaded 28 May 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 28 May 2025Source
  • Form 1FORM-1.pdf · uploaded 29 Jul 2025Source
  • Form 2FORM-2.pdf · uploaded 29 Jul 2025Source
  • Form 3FORM-3 (ABHIMANYU HIGHTS).pdf · uploaded 29 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 29 Jul 2025Source
  • Form 1F1-Q2.pdf · uploaded 20 Oct 2025Source
  • Form 2F2-Q2.pdf · uploaded 20 Oct 2025Source
  • Form 3F3-Q2.pdf · uploaded 20 Oct 2025Source
  • Disclosure of Sold and Booked InventorySU-Q2.pdf · uploaded 20 Oct 2025Source
  • Form 1F1-Q3.pdf · uploaded 12 May 2026Source
  • Form 2FORM-2.pdf · uploaded 12 May 2026Source
  • Form 3FORM-3 (ABHIMANYU HIGHTS).pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySU-Q3.pdf · uploaded 12 May 2026Source
  • Form 1F1-Q4.pdf · uploaded 12 May 2026Source
  • Form 2FORM-2-Q4.pdf · uploaded 12 May 2026Source
  • Form 3F3-Q4 (ABHIMANYU HIGHTS).pdf · uploaded 12 May 2026Source
  • Disclosure of Sold and Booked InventorySU-Q4.pdf · uploaded 12 May 2026Source
  • Form 1F1-Q1.pdf · uploaded 3 Aug 2026Source
  • Form 2FORM-2.pdf · uploaded 3 Aug 2026Source
  • Form 3F 3 - ABHIMANYU HIGHTS.pdf · uploaded 3 Aug 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD.pdf · uploaded 3 Aug 2026Source

Technical

  • DocumentD.pdf · uploaded 14 Oct 2022Source
  • DocumentE (2).pdf · uploaded 1 Nov 2022Source
  • Other – Technical1 Copy of Layout Approval (in case of layout) (13).pdf · uploaded 27 Dec 2023Source
  • Other – TechnicalForm 1- Abhimkanyu Hights.pdf · uploaded 27 Dec 2023Source
  • Other – TechnicalForm 2- Abhimanyu.pdf · uploaded 27 Dec 2023Source
  • Other – Technical2 Commencement Certificates _ NA Order for plotted development (1).pdf · uploaded 8 Jan 2024Source

Technical (Architect)

  • DocumentEngineer certificate - 1 update.pdf · uploaded 6 May 2024Source
  • DocumentFORM-1-MARCH-24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-1-JUNE-24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-1-SEPT-24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-1-DEC-24.pdf · uploaded 16 Jan 2025Source
  • DocumentF1.pdf · uploaded 20 Apr 2025Source
  • DocumentFORM-1.pdf · uploaded 20 Apr 2025Source

Technical (Engineer)

  • Document_Architect's Certificate update.pdf · uploaded 6 May 2024Source
  • DocumentFORM-2-MARCH-24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-2-JUNE-24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-2-SEPT-24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-2-DEC 24.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM-2.pdf · uploaded 20 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals38/1

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Address
38/1, Bhigwan Baramati Road, RuiPIN 413102
Village
Rui, Baramati taluka
Designated bank account
171
Developed in phases
No

Survey, CTS, gat or plot numbers

38/1

Boundaries

North
Part Of Plot No 38
South
Open Space Of Plot No 38
East
12 Mt Wide Road
West
Vp Collage

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNilam Yadav—
Chartered accountantCA Pravin Pise and Associates—
EngineerNilam Yadav—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology