Residential / Group Housing · 1 building · 25 unitsRERA P52100027883

City Icon

Its promised completion date, Jun 2024, has passed and MahaRERA does not show it completed; no MahaRERA orders on record; 100% of its units are booked.

Pune (M Corp.), Pune 411030 · Promoter: Ganesh Somnath Bhokre

Delivery2 yrs 4 mo past duePromised Jun 2024 · no extension on record · not shown completedRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales100% booked25 of 25 units · as the promoter reported to MahaRERA
City Icon project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Its promised completion date, Jun 2024, has passed and MahaRERA does not show it completed

  • This projectRegistered 10 Jan 2021, completion promised 30 Jun 2024, and still not shown completed today.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100027883
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002788310 Jan 202130 Jun 202430 Jun 2024Ganesh Somnath BhokreProject page
Documents65

1 document held by Deedo, 64 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardGANESH PAN CARD (1).pdf · uploaded 2 Dec 2020Source

Legal

  • Legal Title reportSERACH TITLE_compressed.pdf · uploaded 2 Dec 2020Source
  • Declaration Form BForm B Rera city icon_compressed.pdf · uploaded 2 Dec 2020Source

Migrated

  • 1 PAN CardGANESH PAN CARD (1).pdf · uploaded 2 Dec 2020Source
  • 1 Copy of the legal title reportSERACH TITLE_compressed.pdf · uploaded 2 Dec 2020Source
  • 1 Details of encumbrancesemcumbrance.pdf · uploaded 2 Dec 2020Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT_compressed.pdf · uploaded 2 Dec 2020Source
Show all 65 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentplan-2_compressed.pdf · uploaded 2 Dec 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommesment_compressed.pdf · uploaded 2 Dec 2020Source
  • 1 Declaration in FORM BForm B Rera city icon_compressed.pdf · uploaded 2 Dec 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1_compressed.pdf · uploaded 2 Dec 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon form 2.pdf · uploaded 2 Dec 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE CITY ICON_compressed.pdf · uploaded 29 Dec 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentIOD CITY ICON.pdf · uploaded 30 Dec 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)RERA FORM 2A CITY ICON.pdf · uploaded 30 Dec 2020Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER CITY ICON.pdf · uploaded 30 Dec 2020Source
  • 2 Proforma of Allotment letter17 Shinde Agreement to Sale .pdf · uploaded 30 Dec 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc certificate 30 21.pdf · uploaded 27 Jun 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc certificate.pdf · uploaded 27 Jun 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc certificate.pdf · uploaded 27 Jun 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc certificate.pdf · uploaded 27 Jun 2023Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc certificate.pdf · uploaded 27 Jun 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)30 12 21.pdf · uploaded 27 Jun 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)30 3 22.pdf · uploaded 27 Jun 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)30 6 22.pdf · uploaded 27 Jun 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)30 9 22.pdf · uploaded 27 Jun 2023Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)30 12 22.pdf · uploaded 27 Jun 2023Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)343A RERA CERTIFICATE.pdf · uploaded 8 Jul 2023Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)343A city icon RERA CERTIFICATE.pdf · uploaded 8 Jul 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon March 2023.pdf · uploaded 8 Jul 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon June 2023.pdf · uploaded 8 Jul 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon December 2021.pdf · uploaded 8 Jul 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)CamScanner 07-08-2023.pdf · uploaded 8 Jul 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon June 2022.pdf · uploaded 8 Jul 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon November 2022.pdf · uploaded 8 Jul 2023Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon December 2022.pdf · uploaded 8 Jul 2023Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon March 2023.pdf · uploaded 8 Jul 2023Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)city icon June 2023.pdf · uploaded 8 Jul 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (AUG-21) (2)_compressed.pdf · uploaded 10 Jul 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (DEC-21) (1)_compressed.pdf · uploaded 10 Jul 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (MARCH-22) (1)_compressed.pdf · uploaded 10 Jul 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (JUNE-22) (1)_compressed.pdf · uploaded 10 Jul 2023Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (SEPT-22) (1)_compressed.pdf · uploaded 10 Jul 2023Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (DEC-22) (1)_compressed.pdf · uploaded 10 Jul 2023Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (MARCH-23)_compressed.pdf · uploaded 10 Jul 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA FORM-3 (JUNE-23)_compressed.pdf · uploaded 10 Jul 2023Source
  • 1 Disclosure of sold/ booked inventoryCity Icon Sold Unsold Flats (3).pdf · uploaded 29 Jul 2023Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 sep 2021.pdf · uploaded 12 Oct 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1 30 sep 2023.pdf · uploaded 12 Oct 2023Source
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 sep 2023.pdf · uploaded 12 Oct 2023Source
  • 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 (1).pdf · uploaded 12 Oct 2023Source
  • 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 sep 2023.pdf · uploaded 12 Oct 2023Source
  • 2 Disclosure of sold/ booked inventorydec 2021.pdf · uploaded 12 Oct 2023Source
  • 3 Disclosure of sold/ booked inventorymarch 2022.pdf · uploaded 12 Oct 2023Source
  • 4 Disclosure of sold/ booked inventoryjune 2022.pdf · uploaded 12 Oct 2023Source
  • 5 Disclosure of sold/ booked inventorysept 2022.pdf · uploaded 12 Oct 2023Source
  • 6 Disclosure of sold/ booked inventorydec 2022.pdf · uploaded 12 Oct 2023Source
  • 7 Disclosure of sold/ booked inventorymarch 2023.pdf · uploaded 12 Oct 2023Source
  • 8 Disclosure of sold/ booked inventorysept 2023.pdf · uploaded 12 Oct 2023Source

Technical

  • DocumentLAYOUT_compressed.pdf · uploaded 2 Dec 2020Source
  • Documentplan-2_compressed.pdf · uploaded 2 Dec 2020Source
  • DocumentIOD CITY ICON.pdf · uploaded 30 Dec 2020Source

Technical (Architect)

  • Documentform 1 30 sep 2023.pdf · uploaded 12 Oct 2023Source

Technical (Engineer)

  • Documentform 2 sep 2023.pdf · uploaded 12 Oct 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals343 A

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, 2BHK, 3BHK25 units in all
Address
343 A, Shaniwar Peth, PunePIN 411030
Village
Pune (M Corp.), Pune City taluka
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

343 A

Boundaries

North
By Mehendale Maruti Lain
South
By Part Of City S No 343a
East
By City S No 342 De Society Navin Marathi School
West
By City S No 344 Lakshmi Apartment

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking25 units

25 of 25 units booked (100%), as the promoter reported to MahaRERA

1BHK · 16 units1RK · 2 units2BHK · 5 units3BHK · 2 units
TypeCarpet areaUnitsBooked
1BHK29.07 sq m · 313 sq ft11
1BHK30.37 sq m · 327 sq ft11
1BHK31.58 sq m · 340 sq ft11
1BHK33.16 sq m · 357 sq ft11
1BHK33.63 sq m · 362 sq ft33
1BHK40.32 sq m · 434 sq ft11
1BHK40.78 sq m · 439 sq ft44
1BHK41.34 sq m · 445 sq ft33
Show all 13 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK51.84 sq m · 558 sq ft11
1RK23.04 sq m · 248 sq ft11
1RK23.05 sq m · 248 sq ft11
2BHK56.11 sq m · 604 sq ft55
3BHK81.8 sq m · 880 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMr Anand Gadiya—
Chartered accountantDavendra Darekar—
EngineerKp Badgujar—
OtherVinay Thorat—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology