Dynamic Imperia Plus A Phase 4A

Certificate Signed

Pisoli, Pune 411048 |Promoter: Vedant Dynamic Associates

24 Aug 2018Registered with MahaRERA
30 Jun 2028Promised completion
30 Oct 2028Revised completionPushed back 4 months
1Building
38Units registered16 booked (42%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Office, Shop38 units in all
Address
4/2/1, 4/2/2, 4/2/4, Behind Dharmawat Petrol pump, pisoliPIN 411048
Designated bank account
171
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
24 Aug 2018
Promised
30 Jun 2028
Revised
30 Oct 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001754524 Aug 201830 Jun 202830 Oct 2028Vedant Dynamic AssociatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Dynamic Imperia Plus A Phase 4A538

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

16 of 38 units booked (42%), as the promoter reported to MahaRERA

Office · 19 unitsShop · 19 units
TypeCarpet areaUnitsBooked
Office22.15 sq m · 238 sq ft30
Office22.36 sq m · 241 sq ft10
Office22.4 sq m · 241 sq ft10
Office22.53 sq m · 243 sq ft30
Office23.1 sq m · 249 sq ft20
Office23.25 sq m · 250 sq ft10
Office23.62 sq m · 254 sq ft10
Office23.63 sq m · 254 sq ft10
Show all 26 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Office23.71 sq m · 255 sq ft10
Office24.66 sq m · 265 sq ft20
Office25.5 sq m · 274 sq ft10
Office37.54 sq m · 404 sq ft10
Office37.61 sq m · 405 sq ft10
Shop22.15 sq m · 238 sq ft33
Shop22.36 sq m · 241 sq ft11
Shop22.4 sq m · 241 sq ft11
Shop22.53 sq m · 243 sq ft33
Shop23.1 sq m · 249 sq ft22
Shop23.25 sq m · 250 sq ft11
Shop23.62 sq m · 254 sq ft11
Shop23.63 sq m · 254 sq ft11
Shop23.71 sq m · 255 sq ft10
Shop24.66 sq m · 265 sq ft22
Shop25.5 sq m · 274 sq ft11
Shop37.54 sq m · 404 sq ft10
Shop37.61 sq m · 405 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 98 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportSearch-Report.pdf · uploaded 9 Aug 2018Source
  • Declaration Form BForm B A bldg-.pdf · uploaded 9 Aug 2018Source
  • OtherVDA Ass Credai Certificate.pdf · uploaded 10 Feb 2020Source

Migrated

  • 1 Copy of the legal title reportSearch-Report.pdf · uploaded 9 Aug 2018Source
  • 1 Details of encumbrancesSearch-Report.pdf · uploaded 9 Aug 2018Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan Imperia Plus.pdf · uploaded 9 Aug 2018Source
  • 2 Copy of Layout Approval (in case of layout)Proposed Plan.pdf · uploaded 9 Aug 2018Source
Show all 99 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Cerificate Imperia Plus.pdf · uploaded 9 Aug 2018Source
  • 1 Declaration in FORM BForm B A bldg-.pdf · uploaded 9 Aug 2018Source
  • 1 Certificates of CA (Form 3)VDA Certificate CA Certificate.pdf · uploaded 9 Aug 2018Source
  • 1 Building Plan Approval (IOD)A bldg Commercial Plan.pdf · uploaded 10 Aug 2018Source
  • 1 Proforma of Allotment letterUnit Sale Agreement Commercial.pdf · uploaded 10 Aug 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5)Form 5 A wing.pdf · uploaded 30 Sep 2019Source
  • 1 OtherVDA Ass Credai Certificate.pdf · uploaded 10 Feb 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)A WING COMMERCIALS.PDF · uploaded 1 Apr 2021Source
  • 1 Declaration about Commencement CertificateDynamic Imperia Plus A Com CC Decla.pdf · uploaded 8 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Imp Engg Cert APhase 4A_compressed.pdf · uploaded 16 Aug 2021Source
  • 1 Disclosure of sold/ booked inventoryImperia Plus A Phase 4A Commercial.pdf · uploaded 16 Aug 2021Source
  • 2 Certificates of CA (Form 3)CA Certificate VDA A Comm.pdf · uploaded 16 Aug 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)IMP A -Arch-Cert_compressed.pdf · uploaded 27 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)ImpA-Phase4A-March20_compressed.pdf · uploaded 8 Sep 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ImpA-Phase 4A-March21_compressed.pdf · uploaded 8 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)CA Form 5 VDA A wing Commercials_FY 2020-21.pdf · uploaded 9 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)CA Form 5_FY 2021-22_Imperia Plus A Phase 4 A - Comm.pdf · uploaded 26 Nov 2022Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers A commercial.pdf · uploaded 15 Mar 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Enginners A Commercial.pdf · uploaded 15 Mar 2023Source
  • 2 Disclosure of sold/ booked inventoryDisclosuer of Inventory A commecial.pdf · uploaded 15 Mar 2023Source
  • 3 Certificates of CA (Form 3)Form 3 CA A commercial_compressed.pdf · uploaded 15 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)1 Annual Audit Report of Statutory CA (Form 5).pdf · uploaded 24 Mar 2023Source
  • 3 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 21 Jul 2023Source
  • 2 Building Plan Approval (IOD)Wing A Commercial.pdf · uploaded 21 Jul 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentNew CC 2022.pdf · uploaded 21 Jul 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Imperia Plus A.pdf · uploaded 3 Oct 2023Source
  • 2 Declaration about Commencement CertificateCC Declaration A Commercial.pdf · uploaded 12 Oct 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 Imperia Plus 4A Comm.pdf · uploaded 12 Oct 2023Source
  • 3 Disclosure of sold/ booked inventoryInventory A commercial.pdf · uploaded 12 Oct 2023Source
  • 4 Certificates of CA (Form 3)CA form 3 A commercial 24-08-2023_compressed.pdf · uploaded 12 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)VDA-A Commercial A4A.pdf · uploaded 1 Nov 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 2 Feb 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 2 Feb 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure of Inventory VDA Imperia Plus A Commercial.pdf · uploaded 2 Feb 2024Source
  • 5 Certificates of CA (Form 3)CA Certificate VDA Imperia Plus A Commercial Signed.pdf · uploaded 2 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Ce Imperia Plus A_Comm Form 1.pdf · uploaded 9 May 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Cert A4A Commercial updation 31-03-2024.pdf · uploaded 9 May 2024Source
  • 5 Disclosure of sold/ booked inventoryInventory A4A -A Commercial -Updation 31-03-2024.pdf · uploaded 9 May 2024Source
  • 6 Certificates of CA (Form 3)Form 3 CA Imperia Plus -A comm updation 31-03-2024.pdf · uploaded 9 May 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 3 Aug 2024Source
  • 6 Disclosure of sold/ booked inventoryDisclosure of Inventory - June 2024.pdf · uploaded 3 Aug 2024Source
  • 7 Certificates of CA (Form 3)CA Certificate - June 2024 - Sign_11zon.pdf · uploaded 3 Aug 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 14 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A_Imperia Plus A.pdf · uploaded 14 Aug 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Quality Assurance Certificate FY 2022-23.pdf · uploaded 16 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 25 Oct 2024Source
  • 2 Certificates of CA (Form 3)CA Certificate - Sept 2024 - Sign.pdf · uploaded 25 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 25 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Inventory - Sept 2024.pdf · uploaded 25 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5_Dynamic Imperia Plus A Phase 4A - Sign.pdf · uploaded 6 Nov 2024Source
  • 1 Certificates of CA (Form 3)CA Certificate - December 2024_Signed_1_Compressed.pdf · uploaded 17 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Inventory - December 2024_Signed.pdf · uploaded 17 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate December 2024.pdf · uploaded 21 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 3 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate - March 2025.pdf · uploaded 30 Apr 2025Source
  • 1 Certificates of CA (Form 3)CA Certificate - March 2025 - Signed.pdf · uploaded 30 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Engineer Cert_Imperia Plus A_4A- March 2025.pdf · uploaded 30 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Inventory - March 2025.pdf · uploaded 30 Apr 2025Source
  • Withdrawal Update Form 1Form 1 Architect Certificate - June 2025.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 2Form 2 Engineer Certificate - June 2025.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate Imperia Plus A 4A - June 2025.pdf · uploaded 22 Jul 2025Source
  • Form 2A (FY 2024-2025)Form 2A Quality Assurance Certificate FY 2024-25.pdf · uploaded 22 Jul 2025Source
  • Withdrawal Update Form 1Form 1_Architect Certificate_Imperia Plus A_4A_Comm.pdf · uploaded 11 Oct 2025Source
  • Withdrawal Update Form 2Form 2_Engineer Certificate_Imperia Plus A_4A.pdf · uploaded 11 Oct 2025Source
  • Withdrawal Update Form 3Form 3_CA Certificate_Imperia Plus A_4A.pdf · uploaded 11 Oct 2025Source
  • Form 5 (FY 2024-2025)CA Form 5_FY 2024-25_Imperia Plus A Phase 4 A - Comm - signed.pdf · uploaded 8 Dec 2025Source
  • Withdrawal Update Form 1Form 1_Architect Certificate_Imperia Plus A_4A_Comm.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 2Form 2_Imperia Plus A-4A_Engi Cert_March 2026.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 3Form 3_Imperia Plus A-4A_CA Cert_March 2026.pdf · uploaded 20 May 2026Source
  • Withdrawal Update Form 1Form 1_Imperia Plus A-4A_Dec 2025.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 1Form 1_Imperia Plus A 4A_Archi Cert_March 2026.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 2Form 2_Imperia Plus A-4A_Dec 2025.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 2Form 2_Imperia Plus A-4A_Engi Cert_March 2026.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 3Form 3_Imperia Plus A-4A_Dec 2025.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 3Form 3_Imperia Plus A-4A_CA Cert_March 2026.pdf · uploaded 29 Jun 2026Source
  • Withdrawal Update Form 1Form 1_Imperia Plus A_4A_June 2026.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 2Form 2_Imperia Plus A_4A_June 2026.pdf · uploaded 14 Aug 2026Source
  • Withdrawal Update Form 3Form 3_Imperia Plus A_4A_June 2026.pdf · uploaded 14 Aug 2026Source

Technical

  • DocumentLayout Plan Imperia Plus.pdf · uploaded 9 Aug 2018Source
  • DocumentProposed Plan.pdf · uploaded 9 Aug 2018Source
  • DocumentA bldg Commercial Plan.pdf · uploaded 10 Aug 2018Source
  • DocumentLayout Plan.pdf · uploaded 21 Jul 2023Source
  • DocumentWing A Commercial.pdf · uploaded 21 Jul 2023Source

Technical (Architect)

  • DocumentForm 1 Architect Certificate.pdf · uploaded 25 Oct 2024Source
  • DocumentForm 1 Architect Certificate December 2024.pdf · uploaded 21 Jan 2025Source
  • DocumentForm 1 Architect Certificate - March 2025.pdf · uploaded 30 Apr 2025Source
  • DocumentForm 1_Imperia Plus A_4A_June 2026.pdf · uploaded 14 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 Engineer Certificate.pdf · uploaded 25 Oct 2024Source
  • DocumentForm 2 Engineer Certificate.pdf · uploaded 3 Feb 2025Source
  • DocumentForm 2_Engineer Cert_Imperia Plus A_4A- March 2025.pdf · uploaded 30 Apr 2025Source
  • DocumentForm 2_Imperia Plus A_4A_June 2026.pdf · uploaded 14 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pisoli, Haveli taluka

Survey, CTS, gat or plot numbers

4/2/14/2/24/2/4

Boundaries

North
sr no 41 B belongs to Mr Sonkar
South
part sr no 4
East
sr no 41 A belong to kiran yepre
West
9 mtr wide road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVilas Suresh Tarawadi—
EngineerRakesh Jadhav—
EngineerRam Ghodake—
Registered real estate agentParesh Lachman Hardwani—

Source: MahaRERA project page. Contact details are not shown.