Parichay Co-Op Housing Society Ltd

Certificate Signed

Peth, Pune 411030 |Promoter: Belvalkar Realtors LLP

Residential / Group HousingRERAP52100055315
14 Mar 2024Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
1Building
24Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
3.5 BHK, 3BHK, Landlord24 units in all
Address
F P No 1000 (P) And Sub Plot No 6 D (Sno 721/1 + 725/2) (Cts 158/C/8), Navi Peth / Sadashiv Peth, Navi Peth /Sadahshiv PethPIN 411030
Designated bank account
82
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.50642, 73.83864
Parichay Co-Op Housing Society Ltd is at latitude 18.50642, longitude 73.83864.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
14 Mar 2024
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005531514 Mar 202431 Mar 202731 Jul 2027Belvalkar Realtors LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Parichay Co-Op Housing Society624

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 24 units booked (0%), as the promoter reported to MahaRERA

3.5 BHK · 3 units3BHK · 9 unitsLandlord · 12 units
TypeCarpet areaUnitsBooked
3.5 BHK119.24 sq m · 1,283 sq ft30
3BHK57.83 sq m · 622 sq ft10
3BHK83.89 sq m · 903 sq ft10
3BHK92.94 sq m · 1,000 sq ft30
3BHK93.36 sq m · 1,005 sq ft10
3BHK94.15 sq m · 1,013 sq ft20
3BHK103.13 sq m · 1,110 sq ft10
Landlord78.24 sq m · 842 sq ft20
Show all 14 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Landlord79.58 sq m · 857 sq ft10
Landlord83.89 sq m · 903 sq ft20
Landlord92.94 sq m · 1,000 sq ft10
Landlord94.15 sq m · 1,013 sq ft10
Landlord95.75 sq m · 1,031 sq ft20
Landlord119.24 sq m · 1,283 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 141 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardBELVALKAR REALTORS LLP.pdf · uploaded 5 Dec 2023Source

Legal

  • Legal Title reportParichay CHS Search Title Report RERA.pdf · uploaded 2 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part1.pdf · uploaded 10 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part2.pdf · uploaded 10 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part3.pdf · uploaded 10 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part4.pdf · uploaded 10 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part5.pdf · uploaded 10 Jan 2024Source
Show all 142 documentsShow fewer documents

Legal

  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part6.pdf · uploaded 10 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part7.pdf · uploaded 10 Jan 2024Source
  • Other – LegalParichay Society POA -18664-2023 Hvl 15_Part8.pdf · uploaded 10 Jan 2024Source
  • Declaration Form BPARICHAY FORM B.pdf · uploaded 10 Jan 2024Source

Migrated

  • 1 PAN CardBELVALKAR REALTORS LLP.pdf · uploaded 5 Dec 2023Source
  • 1 Copy of Layout Approval (in case of layout)P1.pdf · uploaded 5 Dec 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentP1.pdf · uploaded 5 Dec 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentP2.pdf · uploaded 5 Dec 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentP2.pdf · uploaded 5 Dec 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCCP.pdf · uploaded 5 Dec 2023Source
  • 1 Other – TechnicalANN A PARICHAY20240226.pdf · uploaded 18 Dec 2023Source
  • 1 Copy of the legal title reportParichay CHS Search Title Report RERA.pdf · uploaded 2 Jan 2024Source
  • 1 Declaration about Commencement Certificateparichay format d commencement certificate.pdf · uploaded 10 Jan 2024Source
  • 1 Declaration in FORM BPARICHAY FORM B.pdf · uploaded 10 Jan 2024Source
  • 1 CERSAI detailsparichay undertaking.pdf · uploaded 10 Jan 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)parichay form 3 ann D.pdf · uploaded 10 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterparichay no divation allotment letter20240110_16133704.pdf · uploaded 10 Jan 2024Source
  • 1 Deviation Report with respect to model copy of Agreementparichay no divation model agreement.pdf · uploaded 10 Jan 2024Source
  • 1 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part1.pdf · uploaded 10 Jan 2024Source
  • 2 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part2.pdf · uploaded 10 Jan 2024Source
  • 3 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part3.pdf · uploaded 10 Jan 2024Source
  • 4 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part4.pdf · uploaded 10 Jan 2024Source
  • 5 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part5.pdf · uploaded 10 Jan 2024Source
  • 6 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part6.pdf · uploaded 10 Jan 2024Source
  • 7 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part7.pdf · uploaded 10 Jan 2024Source
  • 8 Other – LegalParichay Society POA -18664-2023 Hvl 15_Part8.pdf · uploaded 10 Jan 2024Source
  • 1 Proforma of Allotment letterALLOTMENT LETTER Parichay.pdf · uploaded 11 Jan 2024Source
  • 1 Proforma of Agreement for saleRERA ATS Parichay final draft 09-1-2024.pdf · uploaded 11 Jan 2024Source
  • 1 a Details of encumbrances concerned to Financeparichay no emcumbrances letter finance.pdf · uploaded 13 Jan 2024Source
  • 1 b Details of encumbrances concerned to Legalparichay no emcumbrances letter finance.pdf · uploaded 13 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD PARICHAY CO OP.pdf · uploaded 13 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsBRLLP NAKUL S BELVALKAR.pdf · uploaded 13 Jan 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsSSB ANNEXURE A .pdf · uploaded 13 Jan 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsBRLLP NEEL A BELVALKAR.pdf · uploaded 13 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBRLLP FORMAT A.pdf · uploaded 13 Jan 2024Source
  • 2 a Details of encumbrances concerned to Financeparichay no emcumbrances letter legal.pdf · uploaded 13 Feb 2024Source
  • 2 b Details of encumbrances concerned to Legalparichay no emcumbrances letter legal.pdf · uploaded 13 Feb 2024Source
  • 4 Building Plan Approval / NA Order for plotted developmentParichay 1.pdf · uploaded 6 Jun 2024Source
  • 5 Building Plan Approval / NA Order for plotted developmentParichay 2.pdf · uploaded 6 Jun 2024Source
  • 6 Building Plan Approval / NA Order for plotted developmentParichay 3.pdf · uploaded 6 Jun 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 BRLLP20240605.pdf · uploaded 6 Jun 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 BRLLP20240605.pdf · uploaded 6 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2 A.pdf · uploaded 6 Jun 2024Source
  • 7 Building Plan Approval / NA Order for plotted developmentParichay.pdf · uploaded 19 Jun 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 BRLLP20240605.pdf · uploaded 19 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 BRLLP20240605.pdf · uploaded 19 Jun 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2 A.pdf · uploaded 19 Jun 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 BRLLP20240605.pdf · uploaded 19 Jun 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)PARICHAY FORM 1.pdf · uploaded 26 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)PARICHAY FORM 2.pdf · uploaded 26 Jun 2024Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)PARICHAY FORM 2A.pdf · uploaded 26 Jun 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 PARICHYA- JUNE 2024.pdf · uploaded 6 Mar 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 PARICHYA- SEPT 2024.pdf · uploaded 6 Mar 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 PARICHYA- DEC 2024.pdf · uploaded 6 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD Jun 24 Parichay.pdf · uploaded 6 Mar 2025Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD Sep 24 Parichay.pdf · uploaded 6 Mar 2025Source
  • 3 Disclosure of sold/ booked inventoryFORM 3 PARICHYA- DEC 2024.pdf · uploaded 6 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01_ARCH_PARICHAY_JUNE'24.pdf · uploaded 12 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01_ARCH_PARICHAY_SEPT'24.pdf · uploaded 12 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01_ARCH_PARICHAY_DEC'24.pdf · uploaded 22 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_PARICHAY_JUN'24.pdf · uploaded 27 Mar 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_PARICHAY_SEPT'24.pdf · uploaded 27 Mar 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_PARICHAY_DEC'24.pdf · uploaded 27 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 27 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01 PARICHAY MAR 25.pdf · uploaded 5 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 PARICHYA MARCH 2025.pdf · uploaded 5 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 PARICHAY MAR 25.pdf · uploaded 5 May 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of SOLD UNSOLD PARICHYA DEC 2024.pdf · uploaded 5 May 2025Source
  • 2 Disclosure of sold/ booked inventoryDISCOLSURE OF SOLD UNSOLD PARICHYA.pdf · uploaded 5 May 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A PARICHAY MAR 25.pdf · uploaded 5 May 2025Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM_02A_PARICHAY_MAR'25 (1).pdf · uploaded 5 May 2025Source
  • Form 1FORM 01_ARCH_PARICHAY_DEC'24.pdf · uploaded 21 Nov 2025Source
  • Form 1FORM01_PARICHAY_MAR'25.pdf · uploaded 21 Nov 2025Source
  • Form 1FORM 01_ARCH_PARICHAY_JUNE'24.pdf · uploaded 21 Nov 2025Source
  • Form 1FORM 01_ARCH_PARICHAY_SEPT'24.pdf · uploaded 21 Nov 2025Source
  • Form 2FORM 2_PARICHAY_DEC'24.pdf · uploaded 21 Nov 2025Source
  • Form 2FORM_02_PARICHAY_MAR'25.pdf · uploaded 21 Nov 2025Source
  • Form 2PARICHAY JUN'24 FORM 02(1).pdf · uploaded 21 Nov 2025Source
  • Form 2PARICHAY SEP'24 FORM 02.pdf · uploaded 21 Nov 2025Source
  • Form 3FORM 3 PARICHYA- DEC 2024.pdf · uploaded 21 Nov 2025Source
  • Form 3FORM 3 PARICHYA MARCH 2025.pdf · uploaded 21 Nov 2025Source
  • Form 3Parichay Form03 JUN'24.pdf · uploaded 21 Nov 2025Source
  • Form 3PARICHAY SEP'24 FORM 03.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD Dec 24 Parichay.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD Mar 25 Parichay.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD Jun 24 Parichay.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD Sep 24 Parichay.pdf · uploaded 21 Nov 2025Source
  • Form 1PARICHAY FORM 01 MAR 24.pdf · uploaded 19 Jun 2026Source
  • Form 2PARICHAY FORM 02 MAR 24.pdf · uploaded 19 Jun 2026Source
  • Form 3PARICHAY FORM 03 MAR 24.pdf · uploaded 19 Jun 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD Mar 24 Parichay.pdf · uploaded 19 Jun 2026Source
  • Withdrawal Update Form 1FORM 01 PARICHAY JUN 25.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 1PARICHAY FORM 01 SEP 25.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 2FORM 02 PARICHAY JUN 25.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 2PARICHAY FORM 02 SEP 25.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 3PARICHAY FORM 03 JUN 25.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 3PARICHAY FORM 03 SEP 25.pdf · uploaded 22 Jun 2026Source
  • Withdrawal Update Form 1PARICHAY FORM 01 DEC 25.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 1PARICHAY FORM 01 MAR 26.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2FORM 02 PARICHAY DEC 25.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 2PARICHAY FORM 02 MAR 26.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3PARICHAY FORM 03 DEC 25.pdf · uploaded 23 Jun 2026Source
  • Withdrawal Update Form 3PARICHAY FORM 03 MAR 26.pdf · uploaded 23 Jun 2026Source
  • Form 5 (FY 2023-2024)Parichay Form 5 FY 23-24.pdf · uploaded 1 Jul 2026Source
  • Form 5 (FY 2024-2025)Parichay Form 5 FY 24-25.pdf · uploaded 1 Jul 2026Source
  • Form 2A (FY 2023-2024)FORM 2A PARICHAY MAR 24.pdf · uploaded 11 Jul 2026Source
  • Form 2A (FY 2024-2025)FORM 2A PARICHAY MAR 25.pdf · uploaded 11 Jul 2026Source
  • Withdrawal Update Form 1FORM_01_PARICHAY_JUN 26_organized.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 2FORM_02_PARICHAY_JUN 26.pdf · uploaded 25 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 PARICHYA JUNE 26.pdf · uploaded 25 Jul 2026Source
  • Form 5 (FY 2025-2026)Parichay form 5 FY 25-26.pdf · uploaded 23 Sep 2026Source
  • Form 2A (FY 2025-2026)FORM02A PARICHAY 2026.pdf · uploaded 5 Oct 2026Source

Technical

  • DocumentP1.pdf · uploaded 5 Dec 2023Source
  • DocumentP1.pdf · uploaded 5 Dec 2023Source
  • DocumentP2.pdf · uploaded 5 Dec 2023Source
  • DocumentP2.pdf · uploaded 5 Dec 2023Source
  • Other – TechnicalANN A PARICHAY20240226.pdf · uploaded 18 Dec 2023Source
  • DocumentParichay 1.pdf · uploaded 6 Jun 2024Source
  • DocumentParichay 2.pdf · uploaded 6 Jun 2024Source
  • DocumentParichay 3.pdf · uploaded 6 Jun 2024Source
  • DocumentParichay.pdf · uploaded 19 Jun 2024Source
  • DocumentParichay1.pdf · uploaded 23 Jun 2026Source
  • DocumentParichay2.pdf · uploaded 23 Jun 2026Source
  • DocumentParichay3.pdf · uploaded 23 Jun 2026Source

Technical (Architect)

  • DocumentFORM 01_ARCH_PARICHAY_JUNE'24.pdf · uploaded 12 Mar 2025Source
  • DocumentFORM 01_ARCH_PARICHAY_SEPT'24.pdf · uploaded 12 Mar 2025Source
  • DocumentFORM 01_ARCH_PARICHAY_DEC'24.pdf · uploaded 22 Mar 2025Source
  • DocumentFORM 01 PARICHAY MAR 25.pdf · uploaded 5 May 2025Source
  • DocumentFORM_01_PARICHAY_JUN 26_organized.pdf · uploaded 25 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2_PARICHAY_JUN'24.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 2_PARICHAY_SEPT'24.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 2_PARICHAY_DEC'24.pdf · uploaded 27 Mar 2025Source
  • DocumentFORM 2 PARICHAY MAR 25.pdf · uploaded 5 May 2025Source
  • DocumentFORM_02_PARICHAY_JUN 26.pdf · uploaded 22 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Peth, Haveli taluka

Survey, CTS, gat or plot numbers

F P NO 1000 (P)SUB PLOT NO 6 D (SNO 721/1 + 725/2) (CTS 158/C/8)

Boundaries

North
Fp No 1000 P 4 And Fp No 1000 P 5
South
Fp No 1000 P 5
East
Fp No 1000 P 6a
West
By 30 Feet Wide Tp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Ajau Mule—
Chartered accountantPB Billimoria and Associates—
Chartered accountantSudhanwa Amitabh Vaidya—
EngineerMubaraka Asif Pathan—
EngineerPooja Ashish Deshpande—
EngineerVivek B Chavan—
EngineerVivek Chavan—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology