Shlok - Phase 1
Certificate SignedNarhe, Pune 411041 |Promoter: Dhankawade Patil Construction
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 3
- Unit types
- 1 BHK, 2 BHK137 units in all
- Address
- SrNo 6/1/19, 6/1/20P, 6/1/22, 6/1/23PIN 411041
- Designated bank account
- 99
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years
The latest completion date on record passed 4 years and 10 months ago.
- Registered
- 28 Jul 2017
- Promised
- 31 Dec 2019
- Revised
- 30 Dec 2021
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100001466 | 28 Jul 2017 | 31 Dec 2019 | 30 Dec 2021 | Dhankawade Patil Construction | Project page |
3 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| A Building | 13 | 43 |
| B Building | 14 | 47 |
| C Building | 14 | 47 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
132 of 137 units booked (96%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A Building | 1 BHK | 35.64 sq m · 384 sq ft | 22 | 22 |
| A Building | 2 BHK | 50.37 sq m · 542 sq ft | 21 | 19 |
| B Building | 2 BHK | 50.2 sq m · 540 sq ft | 1 | 1 |
| B Building | 2 BHK | 50.37 sq m · 542 sq ft | 12 | 12 |
| B Building | 2 BHK | 51.37 sq m · 553 sq ft | 11 | 10 |
| B Building | 2 BHK | 51.87 sq m · 558 sq ft | 12 | 12 |
| B Building | 2 BHK | 52.87 sq m · 569 sq ft | 11 | 11 |
| C Building | 1 BHK | 35.64 sq m · 384 sq ft | 24 | 24 |
| C Building | 2 BHK | 50.37 sq m · 542 sq ft | 23 | 21 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 38 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD.PDF · uploaded 22 Jul 2017Source
Legal
Show all 40 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 22 Jul 2017Source
- 1 Building Plan Approval (IOD)A TYPE - 1.pdf · uploaded 22 Jul 2017Source
- 2 Building Plan Approval (IOD)A TYPE - 2.pdf · uploaded 22 Jul 2017Source
- 3 Building Plan Approval (IOD)B TYPE - 1.pdf · uploaded 22 Jul 2017Source
- 4 Building Plan Approval (IOD)B TYPE - 2.pdf · uploaded 22 Jul 2017Source
- 5 Building Plan Approval (IOD)C TYPE - 1.pdf · uploaded 22 Jul 2017Source
- 6 Building Plan Approval (IOD)C TYPE - 2.pdf · uploaded 22 Jul 2017Source
- 7 Building Plan Approval (IOD)CLUB HOUSE.pdf · uploaded 22 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 22 Jul 2017Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 22 Jul 2017Source
- 1 Proforma of Allotment letterPROFORMA - AGREEMENT.pdf · uploaded 22 Jul 2017Source
- 1 Certificates of CA (Form 5)FORM 5.pdf · uploaded 15 Oct 2018Source
- 2 Certificates of CA (Form 5)RERA -DPC 217-2018.pdf · uploaded 20 Dec 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)DHANKAWADE PATIL FORM 5.pdf · uploaded 20 Dec 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5.pdf · uploaded 9 Jul 2021Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 9 Jul 2021Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPART COMPLICATION SITE - SHLOK-compressed-compressed.pdf · uploaded 5 Jan 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA CERTIFICATE - FORM 5 DPC.pdf · uploaded 21 Jan 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA CERTIFICATE - FORM 5 DPC.pdf · uploaded 21 Jan 2022Source
Technical
- DocumentA TYPE - 1.pdf · uploaded 22 Jul 2017Source
- DocumentA TYPE - 2.pdf · uploaded 22 Jul 2017Source
- DocumentB TYPE - 1.pdf · uploaded 22 Jul 2017Source
- DocumentB TYPE - 2.pdf · uploaded 22 Jul 2017Source
- DocumentLAYOUT.pdf · uploaded 22 Jul 2017Source
- DocumentC TYPE - 1.pdf · uploaded 22 Jul 2017Source
- DocumentC TYPE - 2.pdf · uploaded 22 Jul 2017Source
- DocumentCLUB HOUSE.pdf · uploaded 22 Jul 2017Source
Technical (Architect)
- DocumentARCHITECT CERTIFICATE.pdf · uploaded 22 Jul 2017Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE.pdf · uploaded 22 Jul 2017Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Narhe, Haveli taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- SrNo 6-1-18 - Row House
- South
- SrNo 13P
- East
- SrNo 5P
- West
- SrNo 6-1-20
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | A Vikas Achalkar | — |
| Engineer | G A Bhilare Pvt Ltd | — |
| Other | P D Construction | — |
| Registered real estate agent | Suraj Info Pvt Ltd | — |
Source: MahaRERA project page. Contact details are not shown.