A-11 · Easterlia Phase 2
Lohgaon · RERA P52100034658
IDBLD_0424188 floorsPromised date passed
8Sanctioned habitable floorsregistration certificate
31 Dec 2025Revised completionpromised 31 Dec 2025
17 of 24Units bookedMahaRERA project page
Floors
8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100034658 · registered 20 Apr 2022
- Promised completion
- 31 Dec 2025
- Revised completion
- 31 Dec 2025
- Sanctioned habitable floors
- 8
- ProjectId
- 31,644
- ProjectName
- Easterlia Phase 2
- TotalUnitCount
- 0
- ProjectBuildingId
- 62,042
- BuildingNameNumber
- A-11
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100034658
- ProjectBuildingWingsId
- 62,042
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- A-11
- NoOfBuildingWingFloorProposed
- 8
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 8
Registered transactions
2 registered documents placed in this tower by the deed's own tower token. The Index II opens inside Deedo.
| Registered | Unit | Type | Consideration | ₹ / sq.ft | Document |
|---|---|---|---|---|---|
| 8 Sep 2026 | Rental | ≈ ₹40,000 | — | ||
| 29 Aug 2026 | Rental | ≈ ₹50,000 | — |
Flats with registered documents
2 flats of 2 known flats, highest floor first. Each flat page is its property passport.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1.5 BHK | 46.2 m² (498 sq.ft) | 6 | 3 |
| 1BHK | 35.9 m² (386 sq.ft) | 6 | 5 |
| 2BHK | 50.8 m² (547 sq.ft) | 12 | 9 |
| Total | 24 | 17 |