Skip to content
Deedo home
Menu

Yoganand Park 2

Certificate Signed

Kothrud, Pune 411038 |Promoter: Belvalkar Housing LLP

Residential / Group HousingRERAP52100051502
23 Jun 2023Registered with MahaRERA
31 Dec 2025Promised completion
1Building
6Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2.5 BHK, 2BHK, 3BHK6 units in all
Address
Plot No 2 Cts No 1122 S No 91/1/13 Lokmanya Colony Kothrud, Lokmanya Colony, KothrudPIN 411038
Designated bank account
82
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.51091, 73.80604
Yoganand Park 2 is at latitude 18.51091, longitude 73.80604.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

The latest completion date on record passed 10 months ago.

Registered
23 Jun 2023
Promised
31 Dec 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005150223 Jun 202331 Dec 202531 Dec 2025Belvalkar Housing LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Yoganand Park 276

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 6 units booked (0%), as the promoter reported to MahaRERA

2.5 BHK · 1 unit2BHK · 2 units3BHK · 3 units
TypeCarpet areaUnitsBooked
2.5 BHK68.21 sq m · 734 sq ft10
2BHK14.12 sq m · 152 sq ft10
2BHK22.11 sq m · 238 sq ft10
3BHK16.72 sq m · 180 sq ft10
3BHK78.95 sq m · 850 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 114 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardBHS LLP.pdf · uploaded 11 Apr 2023Source

Legal

  • Declaration Form BRERA declaraction Yoganand promoter.pdf · uploaded 14 Apr 2023Source
  • Declaration Form BSearch and Title Report-Yoganand Park-2.pdf · uploaded 11 Jun 2026Source

Migrated

  • 1 Building Plan Approval / NA Order for plotted development01_YP.pdf · uploaded 10 Apr 2023Source
  • 2 Building Plan Approval / NA Order for plotted development02_YP.pdf · uploaded 10 Apr 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentyoganand park CC.pdf · uploaded 10 Apr 2023Source
  • 1 PAN CardBHS LLP.pdf · uploaded 11 Apr 2023Source
Show all 115 documentsShow fewer documents

Migrated

  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Yoganand Park II Architect Certificate.pdf · uploaded 11 Apr 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Yoganand Park II Engineer Certificate.pdf · uploaded 11 Apr 2023Source
  • 1 Copy of Layout Approval (in case of layout)01_YP.pdf · uploaded 12 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.PDF · uploaded 13 Apr 2023Source
  • 1 Deviation Report with respect to Allotment letterNo Deviation_allotment letter.pdf · uploaded 13 Apr 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo Deviation_agreement.pdf · uploaded 13 Apr 2023Source
  • 2 Deviation Report with respect to model copy of AgreementNo Deviation_agreement.pdf · uploaded 13 Apr 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about CC.PDF · uploaded 14 Apr 2023Source
  • 1 Declaration in FORM BRERA declaraction Yoganand promoter.pdf · uploaded 14 Apr 2023Source
  • 1 Proforma of Agreement for saleYoganand_Park_-2 Agreementt.pdf · uploaded 14 Apr 2023Source
  • 1 Proforma of Allotment letterAllottment Letter.pdf · uploaded 14 Apr 2023Source
  • 1 a Details of encumbrances concerned to FinanceLegal Encumbrance.pdf · uploaded 26 Apr 2023Source
  • 1 b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 26 Apr 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of sold and unsold.pdf · uploaded 26 Apr 2023Source
  • 2 a Details of encumbrances concerned to FinanceNil Encumbrance.pdf · uploaded 19 May 2023Source
  • 2 b Details of encumbrances concerned to LegalNil Encumbrance.pdf · uploaded 19 May 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A ASB.PDF · uploaded 19 May 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A SSB.PDF · uploaded 19 May 2023Source
  • 2 Proforma of Allotment letterANNEXURE I- MODEL FORM OF ALLOTMENT LETTER.pdf · uploaded 19 May 2023Source
  • 1 Copy of the legal title reportlegal title report yoganand park 2.pdf · uploaded 22 May 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE.pdf · uploaded 25 May 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 2 Jun 2023Source
  • 2 CERSAI detailsUndertaking Letter (1).pdf · uploaded 10 Jun 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 yoganand park 2.pdf · uploaded 5 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)YOGANAND_ARCH20240203_18475344.pdf · uploaded 8 Feb 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)YOGANAND_ENGG20240203_18292345.pdf · uploaded 8 Feb 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCH_CERTIFICATE_SEPT_23_YOGANAND.pdf · uploaded 16 Dec 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)YOGANAND PARK FORM 3- SEPT 2023.pdf · uploaded 16 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGG_CERTIFICATE_SEPT_23_YOGANAND.pdf · uploaded 16 Dec 2024Source
  • 4 Disclosure of sold/ booked inventoryYOGANAND PARK FORM 3- SEPT 2023.pdf · uploaded 16 Dec 2024Source
  • 5 Disclosure of sold/ booked inventoryYP- DICLOSURE OF SOLD BOOK INVENTORY -SEPT 23.pdf · uploaded 16 Dec 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsYP- DICLOSURE OF SOLD BOOK INVENTORY -SEPT 23.pdf · uploaded 16 Dec 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)YP FORM 3- MARCH 2024.pdf · uploaded 16 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)YP FORM 3- JUNE 2024.pdf · uploaded 16 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)YP FORM 3- SEPT 2024.pdf · uploaded 16 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 2024-YP.pdf · uploaded 16 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JUNE 2024-YP.pdf · uploaded 16 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MARCH 2024-YP.pdf · uploaded 16 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)YOGANAND PARK FORM 5- FY 2023-24.pdf · uploaded 16 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryYP SOLD DISCLOSURE MAR 24.pdf · uploaded 17 Jan 2025Source
  • 2 Disclosure of sold/ booked inventoryYP SOLD DISCLOSURE JUNE 24.pdf · uploaded 17 Jan 2025Source
  • 3 Disclosure of sold/ booked inventoryYP SOLD DISCLOSURE SEP 24.pdf · uploaded 17 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2 A FY 2023-24-YP.pdf · uploaded 17 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JUNE 2024-YP.pdf · uploaded 6 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MARCH 2024-YP.pdf · uploaded 6 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sep 2024.pdf · uploaded 5 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec 2024.pdf · uploaded 5 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD- YP 2 -DEC 2024.pdf · uploaded 20 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Yoganand Park 2 Dec 2024 Form 3.pdf · uploaded 22 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 02_YOGANAND_DEC'24.pdf · uploaded 22 Mar 2025Source
  • Form 5 (FY 2024-2025)Yoganand Park 2 Form-5.pdf · uploaded 18 Sep 2025Source
  • Withdrawal Update Form 1Form 1_YOganand June 25.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 2FORM 02_YOGANAND_JUNu002725.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 3FORM 3 YOGANAD PARK 2.pdf · uploaded 16 Oct 2025Source
  • Withdrawal Update Form 1FORM_01_YOGANAND_SEPTu002725.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 1FORM_01_YOGANAND_SEPTu002725.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 2FORM_02_YOGANAND_SEPTu002725.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 2FORM_02_YOGANAND_SEPTu002725.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 3FORM 3 YOGANAND PARK II SEPT 2025.pdf · uploaded 18 Nov 2025Source
  • Withdrawal Update Form 3FORM 3 YOGANAND PARK II SEPT 2025.pdf · uploaded 18 Nov 2025Source
  • Form 1FORM 1 MARCH 2024-YP.pdf · uploaded 20 Nov 2025Source
  • Form 2FORM 2 MARCH 2024-YP.pdf · uploaded 20 Nov 2025Source
  • Form 3YP FORM 3- MARCH 2024.pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked InventoryYP SOLD DISCLOSURE MAR 24.pdf · uploaded 20 Nov 2025Source
  • Form 1FORM 1 JUNE 2024-YP.pdf · uploaded 20 Nov 2025Source
  • Form 2FORM 2 JUNE 2024-YP.pdf · uploaded 20 Nov 2025Source
  • Form 3YP FORM 3- JUNE 2024.pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked InventoryYP SOLD DISCLOSURE JUNE 24.pdf · uploaded 20 Nov 2025Source
  • Form 1FORM 1-ARCH CERTIFICATE- SEPT 2024-YP.pdf · uploaded 20 Nov 2025Source
  • Form 2FORM 2 SEPT 2024-YP.pdf · uploaded 20 Nov 2025Source
  • Form 3YP FORM 3- SEPT 2024.pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked InventoryYP SOLD DISCLOSURE SEP 24.pdf · uploaded 20 Nov 2025Source
  • Form 1FORM 01_ARCH_YOGANAND_DEC'24.pdf · uploaded 20 Nov 2025Source
  • Form 2FORM 02_YOGANAND_DEC'24.pdf · uploaded 20 Nov 2025Source
  • Form 3Yoganand Park 2 Dec 2024 Form 3.pdf · uploaded 20 Nov 2025Source
  • Disclosure of Sold and Booked Inventorysold disclosure yp dec'24.pdf · uploaded 20 Nov 2025Source
  • Form 1ARCH_CERTIFICATE_SEPT_23_YOGANAND.pdf · uploaded 21 Nov 2025Source
  • Form 2YOGANAND PARK FORM 02 SEP'23.pdf · uploaded 21 Nov 2025Source
  • Form 3YOGANAND PARK FORM 03 SEP'23.pdf · uploaded 21 Nov 2025Source
  • Disclosure of Sold and Booked Inventorydisclosure of sold&unsold yp sep'23.pdf · uploaded 21 Nov 2025Source
  • Withdrawal Update Form 1FORM01_YOGANAND_DEC 25.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 2FORM_02_YOGANAND_DEC 25.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 2025 YOGANNAD PARK II.pdf · uploaded 16 Feb 2026Source
  • Form 5 (FY 2023-2024)YOGANAND PARK FORM 5- FY 2023-24.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2023-2024)FORM 2 A FY 2023-24-YP.pdf · uploaded 7 Aug 2026Source
  • Form 2A (FY 2025-2026)FORM_02A_YOGANAND_MAR 26.pdf · uploaded 7 Aug 2026Source
  • Occupational CertificateOC Yoganand Park II.pdf · uploaded 7 Aug 2026Source
  • Occupational CertificateOC Verification.pdf · uploaded 7 Aug 2026Source
  • Form 5 (FY 2025-2026)Form 5_Yoganand Park 2_FY 25-26.pdf · uploaded 23 Sep 2026Source

Technical

  • Document01_YP.pdf · uploaded 10 Apr 2023Source
  • Document02_YP.pdf · uploaded 10 Apr 2023Source
  • Document01_YP.pdf · uploaded 12 Apr 2023Source
  • Documentyoganand park 1-3 (1).pdf · uploaded 8 Dec 2025Source
  • Documentyoganand park 2-3 (1).pdf · uploaded 8 Dec 2025Source
  • Documentyoganand park 3-3 (1).pdf · uploaded 8 Dec 2025Source

Technical (Architect)

  • DocumentARCH_CERTIFICATE_SEPT_23_YOGANAND.pdf · uploaded 16 Dec 2024Source
  • DocumentFORM 1 MARCH 2024-YP.pdf · uploaded 6 Feb 2025Source
  • DocumentFORM 1 JUNE 2024-YP.pdf · uploaded 6 Feb 2025Source
  • DocumentForm 1 Sep 2024.pdf · uploaded 5 Mar 2025Source
  • DocumentForm 1 Dec 2024.pdf · uploaded 5 Mar 2025Source
  • DocumentFORM01_YOGANAND_DEC 25.pdf · uploaded 23 Jan 2026Source

Technical (Engineer)

  • DocumentENGG_CERTIFICATE_SEPT_23_YOGANAND.pdf · uploaded 16 Dec 2024Source
  • DocumentFORM 2 MARCH 2024-YP.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM 2 JUNE 2024-YP.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM 2 SEPT 2024-YP.pdf · uploaded 16 Jan 2025Source
  • DocumentFORM 02_YOGANAND_DEC'24.pdf · uploaded 22 Mar 2025Source
  • DocumentFORM_02_YOGANAND_DEC 25.pdf · uploaded 29 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kothrud, Haveli taluka

Survey, CTS, gat or plot numbers

PLOT NO 2 CTS NO 1122 S NO 91/1/13 LOKMANYA COLONY KOTHRUD

Boundaries

North
By Plot No 3 And S No 91 Part
South
By S No 91 Part
East
By Nala And S No 116
West
By 80 Feet Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAR Ajay Amle—
ArchitectSiddharth Harischandrakar—
Chartered accountantCA Pushpak Bogati—
Chartered accountantP B Billimoria & Associates—
EngineerMr Vivek Chavan—
EngineerVivek Chavan—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology