Skip to content

Phase 2 - C · Nakshatra

Kothrud · RERA P52100007857

IDBLD_02383713 floorsExtended 36 mo
13Sanctioned habitable floorsregistration certificate
31 Dec 2023Revised completionpromised 30 Dec 2020
23 of 44Units bookedMahaRERA project page

Floors

13 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100007857 · registered 18 Aug 2017
Promised completion
30 Dec 2020
Revised completion
31 Dec 2023
Sanctioned habitable floors
13
ProjectId
9,648
ProjectName
Nakshatra
TotalUnitCount
0
ProjectBuildingId
1,83,767
BuildingNameNumber
Phase 2 - C
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100007857
ProjectBuildingWingsId
1,88,341
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Phase 2 - C
NoOfBuildingWingFloorProposed
13
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
13

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2 BHK63.4 m² (682 sq.ft)4423
Total4423
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology