Shivam Pride
Deedo IDDP-PUN-455QCompletion was pushed back 1 year to Dec 2025, and that date has passed too; no MahaRERA orders on record; 61% of its units are booked.
Kivale, Pune 412101 · Promoter: Gulabrao Suklal Dhangar
Completion was pushed back 1 year to Dec 2025, and that date has passed too
- This projectRegistered 3 Dec 2021, completion promised 31 Dec 2024, revised to 31 Dec 2025, and still not shown completed today.
1 extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
The building
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52100032049
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100032049 | 3 Dec 2021 | 31 Dec 2024 | 31 Dec 2025 | Gulabrao Suklal Dhangar | Project page |
Documents79
2 documents held by Deedo, 77 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card.pdf · uploaded 28 Sep 2021Source
Legal
Migrated
- 1 PAN CardPAN Card.pdf · uploaded 28 Sep 2021Source
Show all 79 documentsShow fewer documents
Migrated
- 1 Copy of the legal title reportsearch and title report_compressed.pdf · uploaded 28 Sep 2021Source
- 1 Copy of Layout Approval (in case of layout)typical floor plan_compressed.pdf · uploaded 28 Sep 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentTerrace floor plan_compressed.pdf · uploaded 28 Sep 2021Source
- 1 Commencement Certificates / NA Order for plotted developmenttalati_compressed.pdf · uploaded 28 Sep 2021Source
- 1 Declaration in FORM Bform b_compressed.pdf · uploaded 28 Sep 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ar cert.pdf · uploaded 28 Sep 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng cert.pdf · uploaded 28 Sep 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ca certificate.pdf · uploaded 28 Sep 2021Source
- 1 Details of encumbrancesencumberence.pdf · uploaded 29 Sep 2021Source
- 1 Proforma of Allotment lettershivam pride Rent Agreement.pdf · uploaded 10 Nov 2021Source
- 1 CERSAI detailstalati_compressed.pdf · uploaded 26 Nov 2021Source
- 1 Declaration about Commencement CertificateDeclaration of commencecement cert.pdf · uploaded 27 Nov 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 24 Feb 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_10012023.pdf · uploaded 24 Feb 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 24 Feb 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_25.pdf · uploaded 8 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_APR SEP 23.pdf · uploaded 8 Mar 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_APR SEP 24.pdf · uploaded 8 Mar 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_JAN MAR 23.pdf · uploaded 8 Mar 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_OCT DEC 24.pdf · uploaded 8 Mar 2025Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_OCT MAR 24.pdf · uploaded 8 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_25.pdf · uploaded 8 Mar 2025Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 Mar 2025Source
- 1 Building Plan Approval / NA Order for plotted developmentscan 516.pdf · uploaded 8 Mar 2025Source
- 2 Building Plan Approval / NA Order for plotted developmentscan 515_11zon.pdf · uploaded 8 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5_22 23.pdf · uploaded 8 Mar 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5_23 24.pdf · uploaded 8 Mar 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1_25.pdf · uploaded 26 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_APR SEP 23.pdf · uploaded 26 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_APR SEP 24.pdf · uploaded 26 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_25.pdf · uploaded 26 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_25.pdf · uploaded 26 Apr 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_25.pdf · uploaded 26 Apr 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_25.pdf · uploaded 26 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5_23 24.pdf · uploaded 26 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 26 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5_22 23.pdf · uploaded 26 Apr 2025Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5_23 24.pdf · uploaded 26 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)F 2A-2022-23 SP.pdf · uploaded 23 Jun 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)F 2A-2022-23 SP.pdf · uploaded 23 Jun 2025Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)F 2A-2023-24 SP.pdf · uploaded 23 Jun 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)F 1-JAN-23 SP.pdf · uploaded 27 Jun 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)F 1-JAN-24 SP.pdf · uploaded 27 Jun 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)F 1-APR-25 SP.pdf · uploaded 27 Jun 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA F3 JAN 25-MAR 25 SP_11zon.pdf · uploaded 27 Jun 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)F 2-APR-25 SP.pdf · uploaded 27 Jun 2025Source
- 1 Other – LegalFORM B 1.pdf · uploaded 27 Jun 2025Source
- 2 Other – LegalFORM B 2.pdf · uploaded 27 Jun 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Quality Assurance Certificate 20219-20.pdf · uploaded 27 Jun 2025Source
- 1 Disclosure of sold/ booked inventorySOLD 2025 SP.pdf · uploaded 27 Jun 2025Source
- 1 Other – TechnicalPERT Chart Creative.pdf · uploaded 27 Jun 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assurance Certificate 2021-22.pdf · uploaded 27 Jun 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)CA F5 2024-25 SP.pdf · uploaded 27 Jun 2025Source
Technical
- Documenttypical floor plan_compressed.pdf · uploaded 28 Sep 2021Source
- DocumentTerrace floor plan_compressed.pdf · uploaded 28 Sep 2021Source
- Documentscan 516.pdf · uploaded 8 Mar 2025Source
- Documentscan 515_11zon.pdf · uploaded 8 Mar 2025Source
- Other – TechnicalPERT Chart Creative.pdf · uploaded 27 Jun 2025Source
Technical (Architect)
- DocumentForm 1.pdf · uploaded 24 Feb 2023Source
- DocumentFORM 1_25.pdf · uploaded 8 Mar 2025Source
- DocumentFORM 1_25.pdf · uploaded 26 Apr 2025Source
- DocumentF 1-JAN-23 SP.pdf · uploaded 27 Jun 2025Source
- DocumentF 1-JAN-24 SP.pdf · uploaded 27 Jun 2025Source
- DocumentF 1-APR-25 SP.pdf · uploaded 27 Jun 2025Source
Technical (Engineer)
- DocumentForm 2_10012023.pdf · uploaded 24 Feb 2023Source
- DocumentFORM 2_25.pdf · uploaded 8 Mar 2025Source
- DocumentFORM 2_25.pdf · uploaded 26 Apr 2025Source
- DocumentFORM 2_25.pdf · uploaded 26 Apr 2025Source
- DocumentFORM 2_25.pdf · uploaded 26 Apr 2025Source
- DocumentFORM 2_25.pdf · uploaded 26 Apr 2025Source
- DocumentF 2-APR-25 SP.pdf · uploaded 27 Jun 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvals74 1A 4, 74 1B 2A
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 2BHK18 units in all
- Address
- 74 1b 2a And 74 1a 4, Regular Track Road, KiwalePIN 412101
- Village
- Kivale, Mawal taluka
- Location
- 18.66032, 73.73142
- Designated bank account
- 203
- Developed in phases
- No
Survey, CTS, gat or plot numbers
Boundaries
- North
- 9 M Access Road Nandu Taras
- South
- 20 Ft Road
- East
- Plot No 12 R L Memane
- West
- Plot Of R Kirve
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking18 units
11 of 18 units booked (61%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 31.45 sq m · 339 sq ft | 5 | 3 |
| 1BHK | 33.67 sq m · 362 sq ft | 5 | 3 |
| 2BHK | 45.66 sq m · 491 sq ft | 4 | 2 |
| 2BHK | 46.47 sq m · 500 sq ft | 4 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ar Sachin Balawant Barawade | — |
| Chartered accountant | DSD assosiates | — |
| Engineer | Ba Patil | — |
Source: MahaRERA project page. Contact details are not shown.