Extended 7 mo8 floorsRERA P52100022161
D, Nirman Milestone
Deedo IDDP-PUN-6341-DMahaRERA has not published a flat-by-flat record for this tower, and no registered deed names it yet.
Median saleNot on recordneeds 3 or more sales
Booked100%25 of 25 · MahaRERA
Completion31 Jul 202430 Dec 2023 · revised
Units & parking in D
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 58.2 m² (627 sq.ft) | 2 | 2 |
| 2BHK | 68 m² (732 sq.ft) | 23 | 23 |
As registered with MahaRERA
- RERA registration
- P52100022161 · registered 4 Sep 2019
- Promised completion
- 30 Dec 2023
- Revised completion
- 31 Jul 2024
- Sanctioned habitable floors
- 8
- Sanctioned floors (incl. basement, stilt, podium)
- 8
- Units declared
- 0
- Homes
- 0
- Shops and offices
- 0
- MahaRERA status
- Certificate Signed
- Deedo ID
- Deedo IDDP-PUN-6341-D
Questions about D
When is D due for completion?
The MahaRERA registration promises 30 Dec 2023, revised to 31 Jul 2024.
How many floors does D have?
8 sanctioned habitable floors, as registered with MahaRERA.
Data through13 Oct 2026SourcesMahaRERA registration and project page · IGR Maharashtra Index IIFloors and units are as registered; a promoter can revise them in later filings. Party names appear only inside an unlocked Index II.Methodology