B Building · Panchratna Hills Phase 2
Katraj · RERA P52100027976
IDBLD_03261215 floorsPromised date passed
15Sanctioned habitable floorsregistration certificate
30 Jun 2026Revised completionpromised 30 Jun 2026
64 of 104Units bookedMahaRERA project page
Floors
15 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100027976 · registered 21 Jan 2021
- Promised completion
- 30 Jun 2026
- Revised completion
- 30 Jun 2026
- Sanctioned habitable floors
- 15
- ProjectId
- 29,067
- ProjectName
- Panchratna Hills Phase 2
- TotalUnitCount
- 104
- ProjectBuildingId
- 1,56,339
- BuildingNameNumber
- B Building
- FsiWithSanctionSqmts
- 15
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 104
- ProjectRegistartionNo
- P52100027976
- ProjectBuildingWingsId
- 1,59,764
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- B Building
- NoOfBuildingWingFloorProposed
- 15
- NoOfBuildingWingFloorHabitable
- 15
- NoOfBuildingWingFloorSanctioned
- 15
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 40.7 m² (438 sq.ft) | 76 | 50 |
| 2BHK | 65.1 m² (701 sq.ft) | 28 | 14 |
| Total | 104 | 64 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology