Panache
Completion date passedKatraj, Pune 411046 |Promoter: Trimurti Sai Nath Infras LLP
Project summary
As registered with MahaRERA
- RERA registrations
- 4
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2018
P52100005287The latest completion date on record passed 7 years and 10 months ago.
- Registered
- 11 Aug 2017
- Promised
- 31 Dec 2018
Completion promised for 31 Jul 2018
P52100006198The latest completion date on record passed 8 years and 3 months ago.
- Registered
- 14 Aug 2017
- Promised
- 31 Jul 2018
Completion promised for 30 Dec 2021
P52100016181The latest completion date on record passed 4 years and 10 months ago.
- Registered
- 20 Apr 2018
- Promised
- 30 Dec 2021
Completion promised for 30 Dec 2021
P52100019294The latest completion date on record passed 4 years and 10 months ago.
- Registered
- 21 Jan 2019
- Promised
- 30 Dec 2021
4 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100005287 | 11 Aug 2017 | 31 Dec 2018 | — | Trimurti Sai Nath Infras LLP | Project page |
| P52100006198 | 14 Aug 2017 | 31 Jul 2018 | — | Trimurti Sai Nath Infras LLP | Project page |
| P52100016181 | 20 Apr 2018 | 30 Dec 2021 | — | Trimurti Sai Nath Infras LLP | Project page |
| P52100019294 | 21 Jan 2019 | 30 Dec 2021 | — | Trimurti Sai Nath Infras LLP | Project page |
Documents
4 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Katraj
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.