The Atrium
Certificate SignedHaveli, Maharashtra 411060 |Promoter: Arhumashtika Life Spaces
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Commercial
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- Shop396 units in all
- Address
- Survey No 27 Hissa No 1/A Plot No 2, Mohammadwadi, PunePIN 411060
- Designated bank account
- 85
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
254 registered documents matched to this project. Consideration is the value declared in the document; the Index II opens inside Deedo.
| Registered | Unit | Type | Consideration | ₹ / sq.ft | Document |
|---|---|---|---|---|---|
| 12 Oct 2026 | Primary sale | — | ≈ ₹8,764 | ||
| 12 Oct 2026 | Primary sale | — | ≈ ₹8,764 | ||
| 9 Oct 2026 | Primary sale | — | ≈ ₹8,671 | ||
| 9 Oct 2026 | Primary sale | — | ≈ ₹8,541 | ||
| 9 Oct 2026 | Primary sale | — | ≈ ₹8,541 | ||
| 9 Oct 2026 | Primary sale | — | ≈ ₹8,671 | ||
| 9 Oct 2026 | Primary sale | — | ≈ ₹8,671 | ||
| 5 Oct 2026 | Primary sale | — | ≈ ₹8,180 | ||
| 15 Sep 2026 | Primary sale | — | ≈ ₹17,961 | ||
| 15 Sep 2026 | Primary sale | — | ≈ ₹10,512 | ||
| 15 Sep 2026 | Primary sale | — | ≈ ₹8,764 | ||
| 15 Sep 2026 | Primary sale | — | ≈ ₹8,764 | ||
| 3 Sep 2026 | Primary sale | — | ≈ ₹9,910 | ||
| 2 Sep 2026 | Primary sale | — | ≈ ₹13,626 | ||
| 2 Sep 2026 | Primary sale | — | ≈ ₹8,541 | ||
| 2 Sep 2026 | Primary sale | — | ≈ ₹8,671 | ||
| 2 Sep 2026 | Primary sale | — | ≈ ₹9,198 | ||
| 17 Aug 2026 | Primary sale | — | ≈ ₹11,148 | ||
| 14 Aug 2026 | Primary sale | — | ≈ ₹15,769 | ||
| 13 Aug 2026 | Primary sale | — | ≈ ₹8,671 | ||
| 13 Aug 2026 | Primary sale | — | ≈ ₹8,360 | ||
| 11 Aug 2026 | Primary sale | — | ≈ ₹15,776 | ||
| 31 Jul 2026 | Primary sale | — | ≈ ₹12,387 | ||
| 24 Jul 2026 | Primary sale | — | ≈ ₹21,058 | ||
| 22 Jul 2026 | Primary sale | — | ≈ ₹15,776 | ||
| 17 Jul 2026 | Primary sale | — | ≈ ₹8,541 | ||
| 17 Jul 2026 | Primary sale | — | ≈ ₹11,148 | ||
| 14 Jul 2026 | Primary sale | — | ≈ ₹9,910 | ||
| 13 Jul 2026 | Primary sale | — | ≈ ₹9,198 | ||
| 29 Jun 2026 | Primary sale | — | ≈ ₹8,052 | ||
| 29 Jun 2026 | Primary sale | — | ≈ ₹8,671 | ||
| 22 Jun 2026 | Primary sale | — | ≈ ₹9,910 | ||
| 19 Jun 2026 | Primary sale | — | ≈ ₹11,102 | ||
| 19 Jun 2026 | Primary sale | — | ≈ ₹11,102 | ||
| 17 Jun 2026 | Primary sale | — | ≈ ₹14,839 | ||
| 17 Jun 2026 | Primary sale | — | ≈ ₹21,907 | ||
| 15 Jun 2026 | Primary sale | — | ≈ ₹26,281 | ||
| 15 Jun 2026 | Primary sale | — | ≈ ₹15,192 | ||
| 15 Jun 2026 | Primary sale | — | ≈ ₹19,819 | ||
| 10 Jun 2026 | Primary sale | — | ≈ ₹14,864 | ||
| 29 May 2026 | Primary sale | — | ≈ ₹12,605 | ||
| 27 May 2026 | Primary sale | — | ≈ ₹9,198 | ||
| 27 May 2026 | Primary sale | — | ≈ ₹9,290 | ||
| 27 May 2026 | Primary sale | — | ≈ ₹9,198 | ||
| 27 May 2026 | Primary sale | — | ≈ ₹8,180 | ||
| 27 May 2026 | Primary sale | — | ≈ ₹27,871 | ||
| 19 May 2026 | Commercial Building | Primary sale | — | ≈ ₹14,455 | |
| 14 May 2026 | Primary sale | — | ≈ ₹10,517 | ||
| 12 May 2026 | Primary sale | — | ≈ ₹8,764 | ||
| 12 May 2026 | Primary sale | — | ≈ ₹47,071 |
The Atrium in numbers
Registered deals, summarised
Deedo has 254 registered documents at The Atrium, from Aug 2024 to Oct 2026: 254 sales. The median registered sale works out to about ₹13,600 per sq ft, at a median of ₹23 L a deal; 0% of sales were resales.
- What is the price per sq ft at The Atrium?
- The median registered sale works out to about ₹13,600 per sq ft, at a median of ₹23 L a deal; 0% of sales were resales.
- How many properties have been sold at The Atrium?
- 254 sales are registered at The Atrium.
- Where does this data come from?
- The figures come from registered documents (Index II) at the Maharashtra sub-registrar offices, matched at The Atrium by Deedo, last updated with deals registered in Oct 2026.
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 21 Jun 2024
- Promised
- 31 Dec 2027
- Revised
- 30 Apr 2028
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100076708 | 21 Jun 2024 | 31 Dec 2027 | 30 Apr 2028 | Arhumashtika Life Spaces | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Commercial Building | 3 | 396 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 396 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 13.5 sq m · 145 sq ft | 4 | 0 |
| Shop | 13.77 sq m · 148 sq ft | 1 | 0 |
| Shop | 14.07 sq m · 151 sq ft | 2 | 0 |
| Shop | 14.14 sq m · 152 sq ft | 78 | 0 |
| Shop | 14.4 sq m · 155 sq ft | 1 | 0 |
| Shop | 15 sq m · 161 sq ft | 101 | 0 |
| Shop | 15.9 sq m · 171 sq ft | 29 | 0 |
| Shop | 16.06 sq m · 173 sq ft | 1 | 0 |
Show all 34 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 17.13 sq m · 184 sq ft | 2 | 0 |
| Shop | 17.76 sq m · 191 sq ft | 1 | 0 |
| Shop | 17.78 sq m · 191 sq ft | 2 | 0 |
| Shop | 20.25 sq m · 218 sq ft | 4 | 0 |
| Shop | 20.78 sq m · 224 sq ft | 53 | 0 |
| Shop | 21.11 sq m · 227 sq ft | 1 | 0 |
| Shop | 21.6 sq m · 233 sq ft | 1 | 0 |
| Shop | 21.64 sq m · 233 sq ft | 2 | 0 |
| Shop | 22.5 sq m · 242 sq ft | 64 | 0 |
| Shop | 22.99 sq m · 247 sq ft | 2 | 0 |
| Shop | 23.08 sq m · 248 sq ft | 2 | 0 |
| Shop | 23.85 sq m · 257 sq ft | 29 | 0 |
| Shop | 24.72 sq m · 266 sq ft | 1 | 0 |
| Shop | 25.69 sq m · 277 sq ft | 1 | 0 |
| Shop | 25.87 sq m · 278 sq ft | 2 | 0 |
| Shop | 26.63 sq m · 287 sq ft | 1 | 0 |
| Shop | 27.32 sq m · 294 sq ft | 1 | 0 |
| Shop | 28 sq m · 301 sq ft | 1 | 0 |
| Shop | 30.05 sq m · 323 sq ft | 1 | 0 |
| Shop | 30.37 sq m · 327 sq ft | 1 | 0 |
| Shop | 36.37 sq m · 391 sq ft | 1 | 0 |
| Shop | 38.58 sq m · 415 sq ft | 1 | 0 |
| Shop | 40.41 sq m · 435 sq ft | 2 | 0 |
| Shop | 42.25 sq m · 455 sq ft | 1 | 0 |
| Shop | 43.1 sq m · 464 sq ft | 1 | 0 |
| Shop | 49.54 sq m · 533 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 147 filings listed on MahaRERA's project page
Finance
- PAN CardARHUMASHTIKA LIFE SPACES PAN CARD (1).pdf · uploaded 8 Apr 2024Source
Legal
- Other – LegalAnnexure A.pdf · uploaded 11 Apr 2024Source
- Other – LegalIMG-20240412-WA0003.pdf · uploaded 12 Apr 2024Source
- Declaration Form BForm B_Promoter.pdf · uploaded 24 Apr 2024Source
- Legal Title reportArhumashtika Title 09 May 2024.pdf · uploaded 13 May 2024Source
- Other – LegalPartnership Deed 3.pdf · uploaded 7 Jun 2024Source
- Other – LegalDeclaration for Name Change in Partnership Deed.pdf · uploaded 7 Jun 2024Source
Show all 148 documentsShow fewer documents
Legal
Migrated
- 1 PAN CardARHUMASHTIKA LIFE SPACES PAN CARD (1).pdf · uploaded 8 Apr 2024Source
- 1 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 8 Apr 2024Source
- 1 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 8 Apr 2024Source
- 2 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 8 Apr 2024Source
- 3 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 8 Apr 2024Source
- 4 Building Plan Approval / NA Order for plotted developmentPlan 5.pdf · uploaded 8 Apr 2024Source
- 5 Building Plan Approval / NA Order for plotted developmentPlan 6.pdf · uploaded 8 Apr 2024Source
- 6 Building Plan Approval / NA Order for plotted developmentPlan 7.pdf · uploaded 8 Apr 2024Source
- 1 Commencement Certificates / NA Order for plotted developmentbuilding cc.pdf · uploaded 8 Apr 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 The Atrium.pdf · uploaded 8 Apr 2024Source
- 1 a Details of encumbrances concerned to FinanceNo emcumbrances Finance.pdf · uploaded 10 Apr 2024Source
- 2 a Details of encumbrances concerned to FinanceNo emcumbrances Legal.pdf · uploaded 10 Apr 2024Source
- 1 b Details of encumbrances concerned to LegalNo emcumbrances Finance.pdf · uploaded 10 Apr 2024Source
- 2 b Details of encumbrances concerned to LegalNo emcumbrances Legal.pdf · uploaded 10 Apr 2024Source
- 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 10 Apr 2024Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Int.pdf · uploaded 10 Apr 2024Source
- 1 Other – LegalAnnexure A.pdf · uploaded 11 Apr 2024Source
- 2 Other – LegalIMG-20240412-WA0003.pdf · uploaded 12 Apr 2024Source
- 1 CERSAI detailsCERSAI Report.pdf · uploaded 23 Apr 2024Source
- 1 Declaration in FORM BForm B_Promoter.pdf · uploaded 24 Apr 2024Source
- 1 Proforma of Allotment letteratrium allotment.pdf · uploaded 7 May 2024Source
- 1 Deviation Report with respect to Allotment letteratrrium deviation allotment.pdf · uploaded 7 May 2024Source
- 2 Disclosure of Interest in Other Real Estate Organizations1.pdf · uploaded 8 May 2024Source
- 3 Disclosure of Interest in Other Real Estate Organizations2.pdf · uploaded 8 May 2024Source
- 4 Disclosure of Interest in Other Real Estate Organizations3.pdf · uploaded 8 May 2024Source
- 5 Disclosure of Interest in Other Real Estate Organizations4.pdf · uploaded 8 May 2024Source
- 1 Copy of the legal title reportArhumashtika Title 09 May 2024.pdf · uploaded 13 May 2024Source
- 2 CERSAI detailsCERSAI.pdf · uploaded 25 May 2024Source
- 3 CERSAI detailsdeclatation of cersai.pdf · uploaded 25 May 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)final atrium form 3_.pdf · uploaded 25 May 2024Source
- 1 Other – TechnicalAnnexure A.pdf · uploaded 25 May 2024Source
- 3 a Details of encumbrances concerned to FinanceLegal Encumbraces_Arhumastika.pdf · uploaded 27 May 2024Source
- 3 b Details of encumbrances concerned to LegalLegal Encumbraces_Arhumastika.pdf · uploaded 27 May 2024Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeperate Bank Account_Atrium_revised.pdf · uploaded 28 May 2024Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report Agreement to Sale 05 June 2024 Final 1.pdf · uploaded 6 Jun 2024Source
- 2 Deviation Report with respect to model copy of AgreementDeviation Report Agreement to Sale 05 June 2024 Final 2.pdf · uploaded 6 Jun 2024Source
- 3 Deviation Report with respect to model copy of AgreementDeviation Report Agreement to Sale 05 June 2024 Final 3.pdf · uploaded 6 Jun 2024Source
- 3 Other – LegalDeclaration for Name Change in Partnership Deed.pdf · uploaded 7 Jun 2024Source
- 4 Other – LegalPartnership Deed 1.pdf · uploaded 7 Jun 2024Source
- 5 Other – LegalPartnership Deed 2.pdf · uploaded 7 Jun 2024Source
- 6 Other – LegalPartnership Deed 3.pdf · uploaded 7 Jun 2024Source
- 7 Other – LegalPartnership Deed 3.pdf · uploaded 7 Jun 2024Source
- 1 Proforma of Agreement for saleDraft Agreement The Atrium.pdf · uploaded 18 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE ATRIUM 12072024.pdf · uploaded 10 Dec 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 THE ATRIUM 2102024.pdf · uploaded 10 Dec 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 THE ATRIUM 09082024.pdf · uploaded 10 Dec 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 THE ATRIUM 19102024.pdf · uploaded 10 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE ATRIUM 12072024.pdf · uploaded 10 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 THE ATRIUM 19102024.pdf · uploaded 10 Dec 2024Source
- 2 Disclosure of sold/ booked inventoryTHE ATRIUM 30062024.pdf · uploaded 18 Dec 2024Source
- 3 Disclosure of sold/ booked inventoryTHE ATRIUM 30092024.pdf · uploaded 18 Dec 2024Source
- 1 Disclosure of sold/ booked inventoryTHE ATRIUM MOHDWAD 31122024.pdf · uploaded 14 Jan 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ATRIUM 31122024.pdf · uploaded 20 Jan 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 ATRIUM 31122024_compressed.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ATRIUM 31122024.pdf · uploaded 20 Jan 2025Source
- 1 a Details of encumbrances concerned to FinanceFianace encumbrance.pdf · uploaded 29 Jan 2025Source
- 1 b Details of encumbrances concerned to LegalFianace encumbrance.pdf · uploaded 29 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryATRIUM MOHDWADI 31032025.pdf · uploaded 8 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 ATRIUM ARHUM ASHTIKA 31032025.pdf · uploaded 28 Apr 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 13 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 16 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 1Form-1.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 2Form-2.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 22 Sep 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 16 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 17 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 20 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 20 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 20 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 29 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 30 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 2The Atrium- Form-2- Engg Certificate- 30-09-25.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 3Form-3 30062025.pdf · uploaded 31 Oct 2025Source
- Withdrawal Update Form 1form 1 atrium.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2form 2 atrium.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3FORM - 03 (2)_11zon.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1the atrium.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 2form 2 atrium.pdf · uploaded 21 Apr 2026Source
- Withdrawal Update Form 3FORM - 03 (2)_11zon.pdf · uploaded 21 Apr 2026Source
- Form 2A (FY 2025-2026)FORM 2A-ATRIUM.pdf · uploaded 26 Jun 2026Source
- Withdrawal Update Form 1FORM-1 ATRIUM.pdf · uploaded 16 Jul 2026Source
- Withdrawal Update Form 2FORM 2 ATRIUM.pdf · uploaded 16 Jul 2026Source
- Withdrawal Update Form 3FORM- 3 ATRIUM_11zon.pdf · uploaded 16 Jul 2026Source
- Form 5 (FY 2024-2025)Form 5_ The Atrium FY 24-25 sign.pdf · uploaded 17 Sep 2026Source
- Form 5 (FY 2025-2026)Arhum Ashtika Form 5.pdf · uploaded 28 Sep 2026Source
Technical
- DocumentPlan 1.pdf · uploaded 8 Apr 2024Source
- DocumentPlan 2.pdf · uploaded 8 Apr 2024Source
- DocumentPlan 3.pdf · uploaded 8 Apr 2024Source
- DocumentPlan 4.pdf · uploaded 8 Apr 2024Source
- DocumentPlan 5.pdf · uploaded 8 Apr 2024Source
- DocumentPlan 6.pdf · uploaded 8 Apr 2024Source
- DocumentPlan 7.pdf · uploaded 8 Apr 2024Source
- Other – TechnicalAnnexure A.pdf · uploaded 25 May 2024Source
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
Survey, CTS, gat or plot numbers
Boundaries
- North
- 6 10 Meter Road
- South
- 6 15 Meter Road
- East
- 6 15 Meter Road
- West
- 6 48 Meter Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Swapnil Dattatray Wagh | — |
| Chartered accountant | SPAK & Co | — |
| Engineer | Dipak Sonawane | — |
Source: MahaRERA project page. Contact details are not shown.