Indrayani Vatika
Completion date passedDehu, Pune 412109 |Promoter: Sanskruti Developers
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2022
P52100028191The latest completion date on record passed 3 years and 10 months ago.
- Registered
- 10 Feb 2021
- Promised
- 30 Dec 2022
Completion pushed back 1 year
P52100032443The latest completion date on record passed 1 year and 4 months ago.
- Registered
- 4 Jan 2022
- Promised
- 30 Jun 2024
- Revised
- 30 Jun 2025
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100028191 | 10 Feb 2021 | 30 Dec 2022 | — | Sanskruti Developers | Project page |
| P52100032443 | 4 Jan 2022 | 30 Jun 2024 | 30 Jun 2025 | Sanskruti Developers | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Dehu
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.