Project summary
As registered with MahaRERA and published on its project page
- Project type
- Plotted
- Status on MahaRERA
- Certificate Signed
- Address
- S No 547/1/2, Charholi, CharholiPIN 412105
- Designated bank account
- 85
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Sep 2023
The latest completion date on record passed 3 years and 1 month ago.
- Registered
- 15 Oct 2021
- Promised
- 30 Sep 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031277 | 15 Oct 2021 | 30 Sep 2023 | 30 Sep 2023 | Shivshankar Construction | Project page |
Documents
1 document held by Deedo, 18 filings listed on MahaRERA's project page
Finance
- PAN CardVishal tapkir pan card.pdf · uploaded 4 Oct 2021Source
Legal
Migrated
- 1 Copy of the legal title reportLegal Report.pdf · uploaded 1 Oct 2021Source
- 1 Copy of Layout Approval (in case of layout)Sanction Plan.pdf · uploaded 1 Oct 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentNA Order Application.pdf · uploaded 1 Oct 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement certificate.pdf · uploaded 1 Oct 2021Source
Show all 19 documentsShow fewer documents
Migrated
- 1 Proforma of Allotment letterSALE DEED DRAFT.pdf · uploaded 1 Oct 2021Source
- 1 PAN CardVishal tapkir pan card.pdf · uploaded 4 Oct 2021Source
- 1 Details of encumbrancesEncumbrance.pdf · uploaded 4 Oct 2021Source
- 1 Declaration about Commencement CertificateCircular 32.pdf · uploaded 4 Oct 2021Source
- 1 Declaration in FORM BFORM B Shivshankar.pdf · uploaded 6 Oct 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Shivshankar Constn Form 3.pdf · uploaded 7 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 final scanned.pdf · uploaded 29 Dec 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentShivshankar Completion Certificate.pdf · uploaded 26 Jul 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 26 Jul 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Charholi, Haveli taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Land Of Survey No 547-1-2
- South
- Land Of Survey No 542
- East
- Land Of Survey No 547-1-2
- West
- Survey No 541
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Patil & Bugade Associates | — |
| Chartered accountant | Pgmj And Associates | — |
| Engineer | Swapnil Ghare | — |
Source: MahaRERA project page. Contact details are not shown.